Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 23, 2018, 09:22 PM
  • Section#03_02_1795_02_1794_4232018.mpg

Date
04/23/2018
W/O
N/A
Weather
Dry
Operator/Surveyor
OSCAR V.
Sewer ID
Z00292
PipeID
P04140
Time
2:22 PM
Certificate
N/A
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
Y0696
Sewer Name
02 MONTEREY PARK RELIEF TRUNK
City
MONTEREY PARK
Loc. details
Other
Location Code
Z
Use of Sewer
Sanitary Sewer
District
District 02
Page No.
12
Purpose
Post-Rehabilitation Survey
Project
20181231SHO_MONTEREY_PARK_RELIEF_TRUNK
Material
NRCP
Shape
Circular
Height
15 in.
Upstream MH
02 1795
Downstream MH
02 1794
Dir. of Survey
Downstream
Length Surveyed
328.9 ft.
Total Length
328.9 ft.
Structural Index
0
Structural Quick
0000
Structural Rating
0
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
0
Overall Quick
Overall Rating
0
Pipe schematic from manhole 02 1795 to 02 1794
MH: 02 1795MH: 02 1794downstream0 ft. MWL - Water Level, 5 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - POST REHAB BEGINS @ MH 179572.7 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"75.6 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"114.6 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"118.3 ft. TF - Tap Factory Made, at 11 o'clock, -, within 8 inches of joint: NO, 4"122.9 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"158.7 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"182.3 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"203.3 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"230.1 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"251 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"271.7 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"292.8 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"310.2 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"328.9 ft. AMH - Downstream Manhole, Survey Ends - POST REHAB ENDS @ MH 1794

Observations (16)

DistanceCodeObservation
114.6TF
292.8TF
122.9TF
0MWL
0AMHPOST REHAB BEGINS @ MH 1795
230.1TF
328.9AMHPOST REHAB ENDS @ MH 1794
158.7TF
271.7TF
251TF
72.7TF
75.6TF
118.3TF
182.3TF
203.3TF
310.2TF

Properties (5)

additional_info
POST REHAB INSPECTION ONLY
custom_field_three
POST REHAB INSPECTION ONLY
custom_field_two
5
customer
LACSD
datetime