Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 25, 2018, 07:12 PM
  • Section#01_02_1793_02_1637_4252018.mpg

Date
04/25/2018
W/O
N/A
Weather
Dry
Operator/Surveyor
OSCAR V.
Sewer ID
Z00292
PipeID
P04138
Time
12:12 PM
Certificate
N/A
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
Y0696
Sewer Name
02 MONTEREY PARK RELIEF TRUNK
City
MONTEREY PARK
Loc. details
Other
Location Code
Z
Use of Sewer
Sanitary Sewer
District
District 02
Page No.
12
Purpose
Post-Rehabilitation Survey
Project
20181231SHO_MONTEREY_PARK_RELIEF_TRUNK
Material
NRCP
Shape
Circular
Height
15 in.
Upstream MH
02 1793
Downstream MH
02 1637
Dir. of Survey
Downstream
Length Surveyed
164.8 ft.
Total Length
164.8 ft.
Structural Index
0
Structural Quick
0000
Structural Rating
0
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
0
Overall Quick
Overall Rating
0
Pipe schematic from manhole 02 1793 to 02 1637
MH: 02 1793MH: 02 1637downstream0 ft. AMH - Upstream Manhole, Survey Begins - POST REHAB BEGINS @ MH 17930 ft. MWL - Water Level, 5 %of cross sectional area25.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4"68 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"89.8 ft. TF - Tap Factory Made, at 12 o'clock, -, within 8 inches of joint: YES, 6"118.3 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4"164.8 ft. AMH - Downstream Manhole, Survey Ends - POST REHAB ENDS @ MH 1637

Observations (7)

DistanceCodeObservation
89.8TF
68TF
118.3TF
0AMHPOST REHAB BEGINS @ MH 1793
164.8AMHPOST REHAB ENDS @ MH 1637
25.1TF
0MWL

Properties (5)

additional_info
POST REHAB INSPECTION ONLY
custom_field_three
POST REHAB INSPECTION ONLY
custom_field_two
5
customer
LACSD
datetime
2018-04-25T12:12:48-07:00