Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Aug 24, 2022, 10:20 AM
  • 22 0964_22 0963_08242022_033533.mp4

Date
08/24/2022
W/O
966849
Weather
Dry
Operator/Surveyor
J. BUENROSTRO
Sewer ID
Z00790
PipeID
P17334
Time
3:20 AM
Certificate
U-715-07000770
System Owner
1
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K10369
Sewer Name
22 BASE LINE TRUNK
City
GLENDORA
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
12
Purpose
Routine Assessment
Project
RFIR_WO_966849_TV22002_AUG2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
22 0964
Downstream MH
22 0963
Dir. of Survey
Downstream
Length Surveyed
355.5 ft.
Total Length
355.5 ft.
Structural Index
3
Structural Quick
3121
Structural Rating
5
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
5
Pipe schematic from manhole 22 0964 to 22 0963
MH: 22 0964MH: 22 0963downstream0 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK0 ft. MWL - Water Level, 15 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 22 09642.3 ft. MGO - General Observation - MAG COATING2.3 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start87.9 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"96.3 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"130.6 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start140.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 4"165 ft. TB - Tap Break-In, at 10 o'clock, -, within 8 inches of joint: NO, 4"197.3 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"246.3 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"254 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 4"286.2 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 4"298.1 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 4"302.2 ft. TB - Tap Break-In, at 12 o'clock, -, within 8 inches of joint: NO, 4"346.6 ft. TFA - Tap Factory Made Active, at 10 o'clock, -, within 8 inches of joint: NO, 4"353.4 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish353.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish355.5 ft. AMH - Downstream Manhole, Survey Ends - 22 0963

Observation photos (2)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.3 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    130.6 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (21)

DistanceCodeObservation
130.6SSS
0MWM
96.3TF
0MGOCONNECTION AT MH 9 O'CLOCK
298.1TF
286.2TF
353.4SSS
2.3MGOMAG COATING
87.9TF
353.4SAP
355.5AMH22 0963
254TFC
302.2TB
197.3TF
0MWL
2.3SAP
140.4TFC
0AMH22 0964
165TB
246.3TF
346.6TFA

Properties (6)

custom_field_three
AGGREGATE PROJECTING, SPALLING
custom_field_two
3
customer
1
datetime
2022-08-24T03:20:45-07:00
documentation
PROPIPE
is_lateral_inspection
false