Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jun 15, 2022, 05:55 AM
  • 14 0404_14 0403_06142022_231947.mp4

Date
06/14/2022
W/O
957004
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00581
PipeID
P18487
Time
10:55 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10147
Sewer Name
14 TRUNK "E"
City
LANCASTER
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
17
Purpose
Routine Assessment
Project
RFIR_WO_957004_TV14025_JUN2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
12 in.
Width
12 in.
Upstream MH
14 0404
Downstream MH
14 0403
Dir. of Survey
Downstream
Length Surveyed
435.7 ft.
Total Length
435.7 ft.
Structural Index
2
Structural Quick
3P2Q
Structural Rating
440
O&M Index
2
O&M Quick
2O00
O&M Rating
162
Overall Index
2
Overall Quick
Overall Rating
602
Pipe schematic from manhole 14 0404 to 14 0403
MH: 14 0404MH: 14 0403downstream0 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MWL - Water Level, 20 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 04042 ft. MWLS - Water Level, Sag in pipe, 10 %of cross sectional area, Start2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start28 ft. MWLS - Water Level, Sag in pipe, 10 %of cross sectional area, Finish28.7 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start41.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"65.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"90 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"92 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"114.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"143.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"167.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"191.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"215.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6", 6"225.8 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"240.6 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"264.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"293.1 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"298.3 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"317.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"341.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"366.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"390.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"415.2 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"433.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish433.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish433.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish435.7 ft. AMH - Downstream Manhole, Survey Ends - 14 0403

Observation photos (3)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    28.7 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

Observations (31)

DistanceCodeObservation
2MWLS
433.8DAGS
0MWM
341.8TFC
191.8TFC
433.8SSS
90TFC
293.1TFC
225.8TBA
240.6TFC
317.1TFC
366.4TFC
28.7DAGS
114.6TFC
298.3TBA
415.2TFC
41.2TFC
433.8SAP
167.4TFC
2SSS
65.7TFC
264.6TFC
92TBA
2SAP
0MWL
0AMH14 0404
435.7AMH14 0403
28MWLS
215.9TFC
390.8TFC
143.2TFC

Properties (7)

additional_info
630063061422201
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-06-14T22:55:10-07:00
documentation
PRO PIPE
is_lateral_inspection
false