Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jul 11, 2022, 09:27 AM
  • 22 1068_22 1067_07112022_024504.mp4

Date
07/11/2022
W/O
962009
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00812
PipeID
P17439
Time
2:27 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10228
Sewer Name
22 IRWINDALE TRUNK, SECTS 2,3,4,&5
City
IRWINDALE
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
18
Purpose
Capital Improvement Program Assesment
Project
RFIR_WO_962009_TV22043_JUL2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
12 in.
Width
12 in.
Upstream MH
22 1068
Downstream MH
22 1067
Dir. of Survey
Downstream
Length Surveyed
297.9 ft.
Total Length
297.9 ft.
Structural Index
3
Structural Quick
3K2K
Structural Rating
296
O&M Index
2
O&M Quick
2K00
O&M Rating
124
Overall Index
2
Overall Quick
Overall Rating
420
Pipe schematic from manhole 22 1068 to 22 1067
MH: 22 1068MH: 22 1067downstream0 ft. MWL - Water Level, 10 %of cross sectional area0 ft. MWM - Water Mark, 40 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 22 10680 ft. MGO - General Observation - COCKROACHES IN MANHOLE2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 12 to 12 o'clock, within 8 inches of joint: YES, Start6.2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start17.5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"54 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"61.9 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"70.2 ft. TFC - Tap Factory Made Capped, at 03 o'clock, -, within 8 inches of joint: NO, 6"71.6 ft. TB - Tap Break-In, at 10 o'clock, -, within 8 inches of joint: NO, 6"76.3 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"82.6 ft. DSZ - Deposits Settled Other, 10 %of cross sectional area, from 05 to 07 o'clock, , within 8 inches of joint: YES, Start - DEBRIS86.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"98.6 ft. DSZ - Deposits Settled Other, 10 %of cross sectional area, from 05 to 07 o'clock, , within 8 inches of joint: YES, Finish119 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"167.4 ft. TFA - Tap Factory Made Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"172.1 ft. TFC - Tap Factory Made Capped, at 03 o'clock, -, within 8 inches of joint: NO, 6"191.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"240.5 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"295.5 ft. SAP - Surface Aggregate Projecting, from 12 to 12 o'clock, within 8 inches of joint: YES, Change295.5 ft. SAP - Surface Aggregate Projecting, from 12 to 12 o'clock, within 8 inches of joint: YES, Finish295.5 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish295.5 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish297.9 ft. MGO - General Observation - CONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK297.9 ft. AMH - Downstream Manhole, Survey Ends - 22 1067297.9 ft. MGO - General Observation - COCKROACHES IN MANHOLE

Observation photos (5)

  • General Observation - COCKROACHES IN MANHOLE

    0 ft. - General Observation - COCKROACHES IN MANHOLE

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 12 to 12 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 12 to 12 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    6.2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Settled Other,  10 %of cross sectional area, from 05 to 07 o'clock,  , within 8 inches of joint: YES, Start - DEBRIS

    82.6 ft. - Deposits Settled Other, 10 %of cross sectional area, from 05 to 07 o'clock, , within 8 inches of joint: YES, Start - DEBRIS

Observations (28)

DistanceCodeObservation
295.5SAP
297.9MGOCONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK
0MWL
172.1TFC
191.9TFC
0MWM
6.2SSS
17.5TFC
98.6DSZ
61.9TBA
82.6DSZDEBRIS
295.5SAP
297.9AMH22 1067
119TFC
76.3TBA
86.7TFC
54TFC
295.5DAGS
0AMH22 1068
70.2TFC
71.6TB
295.5SSS
2DAGS
2SAP
0MGOCOCKROACHES IN MANHOLE
297.9MGOCOCKROACHES IN MANHOLE
240.5TFC
167.4TFA

Properties (7)

additional_info
630098071122001
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-07-11T02:27:56-07:00
documentation
PRO PIPE
is_lateral_inspection
false