Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jul 13, 2022, 05:34 AM
  • 22 1059_22 1058_07122022_224002.mp4

Date
07/12/2022
W/O
962009
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00812
PipeID
P17430
Time
10:34 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10229
Sewer Name
22 IRWINDALE TRUNK, SECTS 2,3,4,&5
City
IRWINDALE
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
24
Purpose
Capital Improvement Program Assesment
Project
RFIR_WO_962009_TV22043_JUL2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
22 1059
Downstream MH
22 1058
Dir. of Survey
Downstream
Length Surveyed
40.2 ft.
Total Length
40.2 ft.
Structural Index
3
Structural Quick
3727
Structural Rating
35
O&M Index
2
O&M Quick
4127
O&M Rating
18
Overall Index
2
Overall Quick
Overall Rating
53
Pipe schematic from manhole 22 1059 to 22 1058
MH: 22 1059MH: 22 1058downstream0 ft. AMH - Upstream Manhole, Survey Begins - 22 10590 ft. MWM - Water Mark, 50 %of cross sectional area0 ft. MWL - Water Level, 20 %of cross sectional area2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start37.9 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish37.9 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish37.9 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish40.2 ft. MGO - General Observation - COCKROACHES IN MANHOLE40.2 ft. AMH - Downstream Manhole, Survey Ends - 22 1058

Observation photos (4)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • General Observation - COCKROACHES IN MANHOLE

    40.2 ft. - General Observation - COCKROACHES IN MANHOLE

Observations (11)

DistanceCodeObservation
0AMH22 1059
0MWM
40.2MGOCOCKROACHES IN MANHOLE
2SAP
37.9DAGS
37.9SSS
2SSS
0MWL
37.9SAP
40.2AMH22 1058
2DAGS

Properties (7)

additional_info
630098071222201
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-07-12T22:34:16-07:00
documentation
PRO PIPE
is_lateral_inspection