Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0May 10, 2022, 09:36 AM
  • H 0580_H 0579_05112022_034802.mp4

Date
05/10/2022
W/O
951821
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00188
PipeID
P11004
Time
2:36 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10107
Sewer Name
H JOINT OUTFALL H - UNIT 8E
City
BALDWIN PARK
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
19
Purpose
Routine Assessment
Project
RFIR_WO_951821_TV15172_MAY2022
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
27 in.
Width
27 in.
Upstream MH
H 0580
Downstream MH
H 0579
Dir. of Survey
Downstream
Length Surveyed
275.8 ft.
Total Length
275.8 ft.
Structural Index
3
Structural Quick
3J2J
Structural Rating
270
O&M Index
2
O&M Quick
412J
O&M Rating
112
Overall Index
2
Overall Quick
Overall Rating
382
Pipe schematic from manhole H 0580 to H 0579
MH: H 0580MH: H 0579downstream0 ft. MWL - Water Level, 25 %of cross sectional area0 ft. MGO - General Observation - COCKROACHES AT MH0 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK0 ft. AMH - Upstream Manhole, Survey Begins - H 05800 ft. MWM - Water Mark, 50 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start10.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"56.1 ft. TB - Tap Break-In, at 02 o'clock, -, within 8 inches of joint: NO, 6"170.8 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"212.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"219.6 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"272 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish272 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish272 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish275.8 ft. MGO - General Observation - COCKROACHES AT MH275.8 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK275.8 ft. AMH - Downstream Manhole, Survey Ends - H 0579

Observation photos (5)

  • General Observation - COCKROACHES AT MH

    0 ft. - General Observation - COCKROACHES AT MH

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • General Observation - COCKROACHES AT MH

    275.8 ft. - General Observation - COCKROACHES AT MH

Observations (19)

DistanceCodeObservation
272SSS
275.8MGOCOCKROACHES AT MH
0MWL
2DAGS
2SAP
10.7TFC
56.1TB
272DAGS
0MGOCOCKROACHES AT MH
275.8MGOCONNECTION AT MH 3 O'CLOCK
0MGOCONNECTION AT MH 3 O'CLOCK
275.8AMHH 0579
0AMHH 0580
219.6TFC
0MWM
170.8TBA
212.1TFC
272SAP
2SSS

Properties (7)

additional_info
630063051022203
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-05-10T02:36:01-07:00
documentation
PRO PIPE
is_lateral_inspection
false