Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 8, 2022, 08:24 AM
  • 14 0062_14 0061_04082022_012409.mp4

Date
04/08/2022
W/O
946842
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00577
PipeID
P18074
Time
1:24 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10033
Sewer Name
14 TRUNK "A"
City
LANCASTER
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
06
Purpose
Routine Assessment
Project
RFIR_WO_946842_TV14039_APR2022
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
24 in.
Upstream MH
14 0062
Downstream MH
14 0061
Dir. of Survey
Downstream
Length Surveyed
429.4 ft.
Total Length
429.4 ft.
Structural Index
3
Structural Quick
5131
Structural Rating
10
O&M Index
3
O&M Quick
4121
O&M Rating
6
Overall Index
3
Overall Quick
Overall Rating
16
Pipe schematic from manhole 14 0062 to 14 0061
MH: 14 0062MH: 14 0061downstream0 ft. MGO - General Observation - CONNECTION AT MH 6 O'CLOCK0 ft. MWM - Water Mark, 50 %of cross sectional area0 ft. MWL - Water Level, 30 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 00622 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start8.1 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start8.2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start50.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"50.4 ft. MGO - General Observation - MAG COAT50.4 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start57.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"102.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"109.7 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"154.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"161.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"205.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"213.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"257.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"266.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"309.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"318.5 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"361.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"370.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"414 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"422.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"427.3 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish427.3 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish427.3 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish427.3 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish429.4 ft. AMH - Downstream Manhole, Survey Ends - 14 0061

Observation photos (4)

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    8.1 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COAT

    50.4 ft. - General Observation - MAG COAT

  • Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    50.4 ft. - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (30)

DistanceCodeObservation
370.3TFC
309.9TFC
427.3SAP
427.3DAGS
50.4TFC
427.3SSS
0MGOCONNECTION AT MH 6 O'CLOCK
161.9TFC
0MWM
318.5TFC
109.7TFC
429.4AMH14 0061
414TFC
102.4TFC
50.4MGOMAG COAT
257.3TFC
0MWL
8.2SSS
0AMH14 0062
266.2TFC
213.8TFC
57.3TFC
422.2TFC
154.1TFC
205.9TFC
50.4SRV
8.1SAP
2DAGS
427.3SRV
361.6TFC

Properties (7)

additional_info
630138040722201
custom_field_three
VISIBLE REINFORCEMENT/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-04-08T01:24:58-07:00
documentation
PRO PIPE
is_lateral_inspection
false