Wastewater/Activity/PacpInspection/1.0Mar 30, 2022, 07:48 AM
  • 15 0358_15 0357_03302022_010330.mp4

Date
03/30/2022
W/O
946844
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00598
PipeID
P12284
Time
12:48 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10026
Sewer Name
15 BALDWIN PARK TRUNK
City
BALDWIN PARK
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
24
Purpose
Routine Assessment
Project
WO_946844_TV15016_APR2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
18 in.
Upstream MH
15 0358
Downstream MH
15 0357
Dir. of Survey
Downstream
Length Surveyed
321.8 ft.
Total Length
321.8 ft.
Structural Index
3
Structural Quick
3100
Structural Rating
3
O&M Index
3
O&M Quick
4121
O&M Rating
6
Overall Index
3
Overall Quick
Overall Rating
9
Pipe schematic from manhole 15 0358 to 15 0357
MH: 15 0358MH: 15 0357downstream0 ft. MGO - General Observation - COCKROACHES IN MH0 ft. AMH - Upstream Manhole, Survey Begins - 15 03580 ft. MWM - Water Mark, 50 %of cross sectional area0 ft. MWL - Water Level, 25 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start20 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"24.4 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"69 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"73.1 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: NO, 6"117.5 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"121.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"171 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"175 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"228 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"234 ft. TB - Tap Break-In, at 02 o'clock, -, within 8 inches of joint: NO, 6"236 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"288.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"293.2 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"316.8 ft. MWL - Water Level, 50 %of cross sectional area319.6 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish319.6 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish321.8 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK321.8 ft. AMH - Downstream Manhole, Survey Ends - 15 0357321.8 ft. MGO - General Observation - COCKROACHES IN MH

Observation photos (4)

  • General Observation - COCKROACHES IN MH

    0 ft. - General Observation - COCKROACHES IN MH

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • General Observation - COCKROACHES IN MH

    321.8 ft. - General Observation - COCKROACHES IN MH

Observations (25)

DistanceCodeObservation
0MGOCOCKROACHES IN MH
321.8MGOCONNECTION AT MH 9 O'CLOCK
121.7TFC
321.8AMH15 0357
24.4TF
0AMH15 0358
321.8MGOCOCKROACHES IN MH
2DAGS
293.2TFC
228TFC
0MWM
316.8MWL
2SAP
117.5TFC
236TFC
171TF
234TB
20TFC
73.1TFC
175TFC
319.6DAGS
319.6SAP
0MWL
69TFC
288.9TFC

Properties (7)

additional_info
630138032922202
custom_field_three
PROJECTING AGGREGATE
custom_field_two
3
customer
1
datetime
2022-03-30T00:48:20-07:00
documentation
PRO PIPE
is_lateral_inspection
false