Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Mar 15, 2022, 09:19 AM
  • 32 1003_32 1002A_03152022_022519.mp4

Date
03/15/2022
W/O
941500
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00841
PipeID
P19449
Time
2:19 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K10009
Sewer Name
32 SOLEDAD CANYON TRUNK, SECTS 1,2,3,&4
City
SANTA CLARITA
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 32
Page No.
09
Purpose
Routine Assessment
Project
RFIR_WO_941500_TV32049_MAR2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
18 in.
Upstream MH
32 1003
Downstream MH
32 1002A
Dir. of Survey
Downstream
Length Surveyed
79.5 ft.
Total Length
79.5 ft.
Structural Index
3
Structural Quick
3121
Structural Rating
5
O&M Index
3
O&M Quick
4121
O&M Rating
6
Overall Index
3
Overall Quick
Overall Rating
11
Pipe schematic from manhole 32 1003 to 32 1002A
MH: 32 1003MH: 32 1002Adownstream0 ft. AMH - Upstream Manhole, Survey Begins - 32 10030 ft. MWL - Water Level, 25 %of cross sectional area0 ft. MWM - Water Mark, 50 %of cross sectional area2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start77.5 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish77.5 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish77.5 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish79.5 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK79.5 ft. AMH - Downstream Manhole, Survey Ends - 32 1002A

Observation photos (3)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (11)

DistanceCodeObservation
0AMH32 1003
77.5SAP
2SSS
77.5DAGS
0MWL
2DAGS
2SAP
0MWM
79.5MGOCONNECTION AT MH 3 O'CLOCK
79.5AMH32 1002A
77.5SSS

Properties (7)

additional_info
630138031422202
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-03-15T02:19:55-07:00
documentation
PRO PIPE
is_lateral_inspection
false