Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Feb 11, 2022, 09:39 AM
  • 20 0130_20 0129A_02112022_014840.mp4

Date
02/11/2022
W/O
936477
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00744
PipeID
P22287
Time
1:39 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K9870
Sewer Name
20 TRUNK "C"
City
PALMDALE
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 20
Page No.
01
Purpose
Routine Assessment
Project
RFIR_WO_936477_TV20027_FEB2022
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
12 in.
Width
12 in.
Upstream MH
20 0129A
Downstream MH
20 0130
Dir. of Survey
Upstream
Length Surveyed
261.7 ft.
Total Length
261.7 ft.
Structural Index
3
Structural Quick
3121
Structural Rating
5
O&M Index
2
O&M Quick
2100
O&M Rating
2
Overall Index
2
Overall Quick
Overall Rating
7
Pipe schematic from manhole 20 0129A to 20 0130
MH: 20 0129AMH: 20 0130upstream0 ft. AMH - Upstream Manhole, Survey Ends - 20 01302.7 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish2.7 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish2.7 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish43.5 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"47.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"140 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"144.5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"241.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"245.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"259.7 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start259.7 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start259.7 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start261.7 ft. MWM - Water Mark, 15 %of cross sectional area261.7 ft. AMH - Downstream Manhole, Survey Begins - 20 0129A261.7 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK261.7 ft. MWL - Water Level, 5 %of cross sectional area

Observation photos (3)

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (17)

DistanceCodeObservation
2DAGS
0MWM
0AMH20 0129A
0MGOCONNECTION AT MH 9 O'CLOCK
2SAP
214.3TFC
20.5TFC
0MWL
261.7AMH20 0130
259SSS
121.7TFC
259SAP
2SSS
259DAGS
16.3TFC
218.2TFC
117.2TFC

Properties (7)

additional_info
630138021022201
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2022-02-11T01:39:40-08:00
documentation
PRO PIPE
is_lateral_inspection