Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Dec 23, 2021, 07:58 AM
  • 05 0095_05 0094_12232021_001020.mp4

Date
12/22/2021
W/O
926779
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00431
PipeID
P05385
Time
11:58 PM
Certificate
U-508-7069
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K9569
Sewer Name
05 DISTRICT #5 MAIN TRUNK
City
HAWTHRONE
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 05
Page No.
17
Purpose
Routine Assessment
Project
RFIR_WO_926779_TV05373_DEC2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
42 in.
Width
18 in.
Upstream MH
05 0095
Downstream MH
05 0094
Dir. of Survey
Downstream
Length Surveyed
240.9 ft.
Total Length
240.9 ft.
Structural Index
4
Structural Quick
5E3H
Structural Rating
290
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
4
Overall Quick
Overall Rating
290
Pipe schematic from manhole 05 0095 to 05 0094
MH: 05 0095MH: 05 0094downstream0 ft. MGO - General Observation - CONNECTION AT THE MH 9 OC'LOCK0 ft. AMH - Upstream Manhole, Survey Begins - 05 00950 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MWL - Water Level, 20 %of cross sectional area2.2 ft. MGO - General Observation - MAG COAT2.3 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start46.7 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start96.6 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start239.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish239.4 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish239.4 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish240.9 ft. MGO - General Observation - CONNECTION AT THE MH 9 OC'LOCK240.9 ft. AMH - Downstream Manhole, Survey Ends - 05 0094

Observation photos (2)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.3 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    96.6 ft. - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (13)

DistanceCodeObservation
0MGOCONNECTION AT THE MH 9 OC'LOCK
239.4SAP
0AMH05 0095
2.3SAP
46.7SSS
2.2MGOMAG COAT
0MWM
96.6SRV
239.4SRV
240.9MGOCONNECTION AT THE MH 9 OC'LOCK
240.9AMH05 0094
239.4SSS
0MWL

Properties (7)

additional_info
630074122221201
custom_field_three
AGGREGATE PROJECTING
custom_field_two
2
customer
1
datetime
2021-12-22T23:58:23-08:00
documentation
PROPIPE
is_lateral_inspection
false