Wastewater/Activity/PacpInspection/1.0Dec 1, 2021, 10:37 AM
  • 14 0244_14 0243_12012021_030634.mp4

Date
12/01/2021
W/O
922057
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00569
PipeID
P18297
Time
2:37 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K9609
Sewer Name
14 AVENUE "H" TRUNK
City
LANCASTER
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
05
Purpose
Routine Assessment
Project
RFIR_WO_922057_TV14037_NOV2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
30 in.
Width
30 in.
Upstream MH
14 0244
Downstream MH
14 0243
Dir. of Survey
Downstream
Length Surveyed
607.2 ft.
Total Length
607.2 ft.
Structural Index
3
Structural Quick
3121
Structural Rating
5
O&M Index
2
O&M Quick
2100
O&M Rating
2
Overall Index
2
Overall Quick
Overall Rating
7
Pipe schematic from manhole 14 0244 to 14 0243
MH: 14 0244MH: 14 0243downstream0 ft. MWM - Water Mark, 35 %of cross sectional area0 ft. MWL - Water Level, 35 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 02442 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - MAG COAT2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start603.9 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish603.9 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish603.9 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish607.2 ft. AMH - Downstream Manhole, Survey Ends - 14 0243

Observation photos (4)

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COAT

    2 ft. - General Observation - MAG COAT

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

Observations (11)

DistanceCodeObservation
603.9SSS
607.2AMH14 0243
0MWM
0MWL
2SAP
2MGOMAG COAT
0AMH14 0244
2SSS
603.9DAGS
2DAGS
603.9SAP

Properties (7)

additional_info
630069113021201
custom_field_three
PROJECTING AGGREGATE/SPALLING
custom_field_two
2
customer
1
datetime
2021-12-01T02:37:22-08:00
documentation
PRO PIPE
is_lateral_inspection
false