08 0476_08 0475_12012021_105730.mp4
2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start
2 ft. - Deposits Settled Other, 5 %of cross sectional area, from 09 to 03 o'clock, , within 8 inches of joint: YES, Start - HANGING DEPOSITS
2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start
5.9 ft. - Surface Reinforcement Corroded, from 09 to 03 o'clock, within 8 inches of joint: YES, Start
9.5 ft. - Deposits Attached Ragging, 10 %of cross sectional area, from 12 to 01 o'clock, , within 8 inches of joint: YES
311.4 ft. - Deposits Attached Other, 15 %of cross sectional area, from 09 to 12 o'clock, , within 8 inches of joint: YES - HANGING PIPE MATERIAL
| Distance | Code | Observation |
|---|---|---|
| 725.8 | SAP | — |
| 311.4 | DAZ | HANGING PIPE MATERIAL |
| 725.8 | SRC | — |
| 2 | MGO | 35% MAG COAT |
| 9.5 | DAR | — |
| 5.9 | SRC | — |
| 0 | AMH | 08 0476 |
| 726.6 | AMH | 08 0475 |
| 725.8 | SSS | — |
| 2 | SAP | — |
| 0 | MWL | — |
| 2 | DSZ | HANGING DEPOSITS |
| 2 | SSS | — |
| 725.8 | DSZ | HANGING |
| 0 | MWM | — |