Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Aug 12, 2021, 06:32 AM
  • 32 1175_32 1174_08112021_234529.mp4

Date
08/11/2021
W/O
906609
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00839
PipeID
P19629
Time
11:32 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K9230
Sewer Name
32 SAN FERNANDO ROAD TRUNK
City
SANTA CLARITA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 32
Page No.
09
Purpose
Routine Assessment
Project
RFIR_WO_906609_TV32021_AUG2021
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
18 in.
Upstream MH
32 1174
Downstream MH
32 1175
Dir. of Survey
Upstream
Length Surveyed
395.1 ft.
Total Length
395.1 ft.
Structural Index
3
Structural Quick
3E00
Structural Rating
93
O&M Index
2
O&M Quick
2O00
O&M Rating
156
Overall Index
2
Overall Quick
Overall Rating
249
Pipe schematic from manhole 32 1174 to 32 1175
MH: 32 1174MH: 32 1175upstream0 ft. AMH - Upstream Manhole, Survey Ends - 32 11750 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK1.4 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish213.6 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: NO, 6"218 ft. TFA - Tap Factory Made Active, at 02 o'clock, -, within 8 inches of joint: NO, 6"236.2 ft. MMC - Material Change, Vitrified clay pipe236.2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish376.3 ft. TBA - Tap Break-In Active, at 12 o'clock, -, within 8 inches of joint: NO, 6"388.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start393.1 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start393.1 ft. MGO - General Observation - MAG COATING THROUGHOUT395.1 ft. MWM - Water Mark, 20 %of cross sectional area395.1 ft. MWL - Water Level, 10 %of cross sectional area395.1 ft. AMH - Downstream Manhole, Survey Begins - 32 1174

Observation photos (4)

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • General Observation - MAG COATING THROUGHOUT

    2 ft. - General Observation - MAG COATING THROUGHOUT

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    6.3 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Material Change, Vitrified clay pipe

    158.9 ft. - Material Change, Vitrified clay pipe

Observations (14)

DistanceCodeObservation
181.5TFC
6.3SAP
0MWM
158.9MMC
2DAGS
0MWL
18.8TBA
2MGOMAG COATING THROUGHOUT
395.1AMH32 1175
177.1TFA
158.9SAP
0AMH32 1174
395.1MGOCONNECTION AT MH 3 O'CLOCK
393.7DAGS

Properties (7)

additional_info
630069081121201
custom_field_three
PROJECTING AGGREGATE
custom_field_two
3
customer
1
datetime
2021-08-11T23:32:39-07:00
documentation
PRO PIPE
is_lateral_inspection
false