Wastewater/Activity/PacpInspection/1.0Jul 2, 2021, 06:15 AM
  • 14 0386_14 0385_07012021_232803.mp4

Date
07/01/2021
W/O
896585
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00581
PipeID
P18466
Time
11:15 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K9018
Sewer Name
14 TRUNK "E"
City
LANCASTER
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
17
Purpose
Routine Assessment
Project
RFIR_WO_896585_TV14025_JUN2021
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
14 0386
Downstream MH
14 0385
Dir. of Survey
Downstream
Length Surveyed
341.5 ft.
Total Length
341.5 ft.
Structural Index
3
Structural Quick
3L2L
Structural Rating
335
O&M Index
2
O&M Quick
412L
O&M Rating
138
Overall Index
2
Overall Quick
Overall Rating
473
Pipe schematic from manhole 14 0386 to 14 0385
MH: 14 0386MH: 14 0385downstream0 ft. MWM - Water Mark, 50 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 03860 ft. MWL - Water Level, 40 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start27.2 ft. TFA - Tap Factory Made Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"55.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"79.5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"104.1 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"128.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"152.1 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"180.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"204.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"229 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"253.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"276.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"293.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"298 ft. TBA - Tap Break-In Active, at 03 o'clock, -, within 8 inches of joint: NO, 6"321.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"339.4 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish339.4 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish339.4 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish341.5 ft. AMH - Downstream Manhole, Survey Ends - 14 0385

Observation photos (3)

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (24)

DistanceCodeObservation
339.4SAP
79.5TFC
128.9TFC
27.2TFA
293.8TFC
339.4SSS
2DAGS
298TBA
2SAP
339.4DAGS
253.8TFC
321.1TFC
152.1TFC
180.3TFC
2SSS
204.4TFC
104.1TFC
0MWM
341.5AMH14 0385
0AMH14 0386
229TFC
276.6TFC
0MWL
55.8TFC

Properties (7)

additional_info
630069070121201
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2021-07-01T23:15:14-07:00
documentation
PRO PIPE
is_lateral_inspection
false