H 0817 _15 0005_20141118_004723.mp4
0 ft. - Downstream Manhole, Survey Begins - 15 0005
0 ft. - Water Mark, 5 %of cross sectional area
0 ft. - Reversal Inspection
0 ft. - General Observation - CONNECTION AT MANHOLE 9 O'CLOCK
0 ft. - Water Level, 5 %of cross sectional area
0 ft. - General Observation - CONNECTION AT MANHOLE 3 O'CLOCK
5.7 ft. - Deposits Settled Fine, 10 %of cross sectional area, from 05 to 07 o'clock, , within 8 inches of joint: YES, Start
18.7 ft. - End of Pipe
18.7 ft. - Deposits Settled Fine, 10 %of cross sectional area, from 05 to 07 o'clock, , within 8 inches of joint: YES, Finish
| Distance | Code | Observation |
|---|---|---|
| 18.7 | AEP | — |
| 0 | AMH | 15 0005 |
| 0 | MWM | — |
| 0 | MGO | — |
| 0 | MGO | CONNECTION AT MANHOLE 9 O'CLOCK |
| 18.7 | DSF | — |
| 0 | MWL | — |
| 0 | MGO | CONNECTION AT MANHOLE 3 O'CLOCK |
| 5.7 | DSF | — |