Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jun 25, 2021, 09:43 AM
  • A 0375_A 0374_06252021_030453.mp4

Date
06/25/2021
W/O
896145
Weather
Dry
Operator/Surveyor
M.MARTINEZ
Sewer ID
Z00325
PipeID
P08285
Time
2:43 AM
Certificate
U-115-06022794
System Owner
1
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K8997
Sewer Name
A JOA-1A SAN JOSE CREEK WRP INTERCEPTOR
City
ROSEMEAD
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
15
Purpose
Routine Assessment
Project
RFIR_WO_896145_TV15260_JUN2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
39 in.
Upstream MH
A 0375
Downstream MH
A 0374
Dir. of Survey
Downstream
Length Surveyed
707.5 ft.
Total Length
707.5 ft.
Structural Index
2
Structural Quick
2200
Structural Rating
4
O&M Index
4
O&M Quick
4100
O&M Rating
4
Overall Index
3
Overall Quick
Overall Rating
8
Pipe schematic from manhole A 0375 to A 0374
MH: A 0375MH: A 0374downstream0 ft. AMH - Upstream Manhole, Survey Begins - A 03750 ft. MWL - Water Level, 20 %of cross sectional area0 ft. MWM - Water Mark, 50 %of cross sectional area2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - MAG COAT368.9 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish368.9 ft. MMC - Material Change, Vitrified clay pipe492.8 ft. MMC - Material Change, Reinforced concrete pipe492.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start707.5 ft. AMH - Downstream Manhole, Survey Ends - A 0374707.5 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

Observation photos (5)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COAT

    2 ft. - General Observation - MAG COAT

  • Material Change, Vitrified clay pipe

    368.9 ft. - Material Change, Vitrified clay pipe

  • Material Change, Reinforced concrete pipe

    492.8 ft. - Material Change, Reinforced concrete pipe

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    492.8 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (11)

DistanceCodeObservation
2SSS
0AMHA 0375
368.9SSS
2MGOMAG COAT
0MWL
707.5AMHA 0374
707.5SSS
0MWM
492.8MMC
368.9MMC
492.8SSS

Properties (7)

custom_field_three
SPALLING MAG COAT
custom_field_two
3
customer
1
datetime
2021-06-25T02:43:59-07:00
documentation
PRO PIPE
is_lateral_inspection
false
year_laid
29462