Wastewater/Activity/PacpInspection/1.0Apr 14, 2021, 10:02 AM
  • 14 0053_14 0052_04142021_032541.mp4

Date
04/14/2021
W/O
886341
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00577
PipeID
P18065
Time
3:02 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K8778
Sewer Name
14 TRUNK "A"
City
LANCASTER
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
06
Purpose
Routine Assessment
Project
RFIR_WO_886341_TV14039_APR2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
24 in.
Upstream MH
14 0053
Downstream MH
14 0052
Dir. of Survey
Downstream
Length Surveyed
509.9 ft.
Total Length
509.9 ft.
Structural Index
3
Structural Quick
5S3S
Structural Rating
1010
O&M Index
2
O&M Quick
412S
O&M Rating
206
Overall Index
3
Overall Quick
Overall Rating
1216
Pipe schematic from manhole 14 0053 to 14 0052
MH: 14 0053MH: 14 0052downstream0 ft. AMH - Upstream Manhole, Survey Begins - 14 00530 ft. MWM - Water Mark, 30 %of cross sectional area0 ft. MWL - Water Level, 25 %of cross sectional area2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - 55% MAG COAT2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"52.7 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"76.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"101.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"125.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"149.6 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"173.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"205.7 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"229.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"254.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"278.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"302.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"326.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"351.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"374.5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"399.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"422.8 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"507.5 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish507.5 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish507.5 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish507.5 ft. SRV - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish509.9 ft. AMH - Downstream Manhole, Survey Ends - 14 0052

Observation photos (3)

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Reinforcement Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

Observations (30)

DistanceCodeObservation
2SAP
125.3TFC
278.7TFC
507.5DAGS
173.4TFC
0AMH14 0053
229.7TFC
2SSS
326.7TFC
374.5TFC
76.9TFC
205.7TFC
399.3TFC
0MWM
422.8TFC
507.5SAP
302.3TFC
5TFC
2SRV
52.7TFC
254.9TFC
149.6TFC
0MWL
2MGO55% MAG COAT
101.3TFC
507.5SSS
351.3TFC
509.9AMH14 0052
2DAGS
507.5SRV

Properties (7)

additional_info
630069041321201
custom_field_three
VISIBLE REINFORCEMENT/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2021-04-14T03:02:33-07:00
documentation
PRO PIPE
is_lateral_inspection
false