Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0May 5, 2021, 06:55 AM
  • 14 0416_14 0415_05052021_001936.mp4

Date
05/04/2021
W/O
890935
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00578
PipeID
P18499
Time
11:55 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K8799
Sewer Name
14 TRUNK "B"
City
LANCASTER
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
07
Purpose
Routine Assessment
Project
RFIR_WO_890935_TV14019_MAY2021
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
14 0416
Downstream MH
14 0415
Dir. of Survey
Downstream
Length Surveyed
347.1 ft.
Total Length
347.1 ft.
Structural Index
3
Structural Quick
3M2M
Structural Rating
345
O&M Index
2
O&M Quick
412M
O&M Rating
142
Overall Index
2
Overall Quick
Overall Rating
487
Pipe schematic from manhole 14 0416 to 14 0415
MH: 14 0416MH: 14 0415downstream0 ft. AMH - Upstream Manhole, Survey Begins - 14 04160 ft. MWM - Water Mark, 60 %of cross sectional area0 ft. MWL - Water Level, 40 %of cross sectional area2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start11.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"35.5 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"63.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"88 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"112.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"136.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"160.7 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"189.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"209.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"262 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"286 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"310.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"334.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"345.6 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish345.6 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish345.6 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish347.1 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK347.1 ft. AMH - Downstream Manhole, Survey Ends - 14 0415

Observation photos (3)

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (24)

DistanceCodeObservation
11.8TFC
160.7TFC
2SSS
334.9TFC
347.1MGOCONNECTION AT MH 3 O'CLOCK
347.1AMH14 0415
112.2TFC
345.6SAP
0AMH14 0416
136.3TFC
2DAGS
286TFC
262TFC
345.6SSS
88TFC
0MWM
0MWL
189.3TFC
310.9TFC
35.5TFC
209.2TFC
2SAP
63.9TFC
345.6DAGS

Properties (7)

additional_info
630069050421201
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2021-05-04T23:55:13-07:00
documentation
PRO PIPE
is_lateral_inspection
false