Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Feb 16, 2021, 11:46 AM
  • H 0117_H 0116_02162021_040053.mp4

Date
02/16/2021
W/O
875062
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00165
PipeID
P10568
Time
3:46 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K8572
Sewer Name
H JOINT OUTFALL H - UNIT 1F
City
HUNTINGTON PARK
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 01
Page No.
04
Purpose
Routine Assessment
Project
RFIR_WO_875062_TV01242_FEB2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
36 in.
Width
36 in.
Upstream MH
H 0117
Downstream MH
H 0116
Dir. of Survey
Downstream
Length Surveyed
458.8 ft.
Total Length
458.8 ft.
Structural Index
3
Structural Quick
3Q2Q
Structural Rating
455
O&M Index
2
O&M Quick
2Q00
O&M Rating
182
Overall Index
2
Overall Quick
Overall Rating
637
Pipe schematic from manhole H 0117 to H 0116
MH: H 0117MH: H 0116downstream0 ft. AMH - Upstream Manhole, Survey Begins - H 01170 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MWL - Water Level, 20 %of cross sectional area2 ft. MGO - General Observation - 60% MAG COAT2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start458.8 ft. AMH - Downstream Manhole, Survey Ends - H 0116458.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish458.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish458.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

Observation photos (3)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (11)

DistanceCodeObservation
458.8AMHH 0116
458.8SSS
0AMHH 0117
0MWM
2MGO60% MAG COAT
2SSS
0MWL
2DAGS
458.8DAGS
2SAP
458.8SAP

Properties (7)

additional_info
630069021521203
custom_field_three
PROJECTING AGGREGATE/SPALLING
custom_field_two
2
customer
1
datetime
2021-02-16T03:46:49-08:00
documentation
PRO PIPE
is_lateral_inspection
false