Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Feb 8, 2021, 12:17 PM
  • 02 2093_02 2092_02082021_044519.mp4

Date
02/08/2021
W/O
870412
Weather
Dry
Operator/Surveyor
M.MARTINEZ
Sewer ID
Z00283
PipeID
P04194
Time
4:17 AM
Certificate
U-115-06022794
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K8395
Sewer Name
02 MONTEBELLO INTERCEPTOR TRUNK, SECTS 1&2
City
COMMERCE
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 02
Page No.
18
Purpose
Routine Assessment
Project
RFIR_WO_870412_TV02213_JAN2021
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
12 in.
Upstream MH
02 2092
Downstream MH
02 2093
Dir. of Survey
Upstream
Length Surveyed
265.3 ft.
Total Length
265.3 ft.
Structural Index
3
Structural Quick
3J2J
Structural Rating
265
O&M Index
2
O&M Quick
412B
O&M Rating
38
Overall Index
2
Overall Quick
Overall Rating
303
Pipe schematic from manhole 02 2092 to 02 2093
MH: 02 2092MH: 02 2093upstream0 ft. MSA - Survey Abandoned - DUE TO DEBRIS0 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish0 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish0 ft. OBR - Obstacles Rocks, 10 %of cross sectional area, at 06 o'clock, Finish86.5 ft. OBR - Obstacles Rocks, 10 %of cross sectional area, at 06 o'clock, Start242 ft. MGO - General Observation - MAG COAT263.3 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start263.3 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start265.3 ft. AMH - Downstream Manhole, Survey Begins - 02 2092265.3 ft. MWL - Water Level, 35 %of cross sectional area265.3 ft. MWM - Water Mark, 50 %of cross sectional area

Observation photos (5)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COAT

    23.3 ft. - General Observation - MAG COAT

  • Obstacles Rocks, 10 %of cross sectional area, at 06 o'clock, Start

    178.8 ft. - Obstacles Rocks, 10 %of cross sectional area, at 06 o'clock, Start

  • Survey Abandoned - DUE TO DEBRIS

    265.3 ft. - Survey Abandoned - DUE TO DEBRIS

Observations (11)

DistanceCodeObservation
0AMH02 2092
265.3MSADUE TO DEBRIS
265.3SSS
2SSS
265.3SAP
0MWL
265.3OBR
23.3MGOMAG COAT
0MWM
178.8OBR
2SAP

Properties (7)

custom_field_three
SPALLING, AGGREGATE PROJECTING
custom_field_two
3
customer
1
datetime
2021-02-08T04:17:33-08:00
documentation
PRO PIPE
is_lateral_inspection
false
year_laid
30160