Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Feb 3, 2021, 08:15 AM
  • 22 0287_22 0286_02032021_003854.mp4

Date
02/03/2021
W/O
870414
Weather
Dry
Operator/Surveyor
M.MARTINEZ
Sewer ID
Z00793
PipeID
P16573
Time
12:15 AM
Certificate
U-115-06022794
System Owner
1
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K8389
Sewer Name
22 CAMERON TRUNK, SECTS 1,2,&3
City
WEST COVINA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
31
Purpose
Routine Assessment
Project
RFIR_WO_870414_TV22014_JAN2021
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
12 in.
Width
12 in.
Upstream MH
22 0286
Downstream MH
22 0287
Dir. of Survey
Upstream
Length Surveyed
326.4 ft.
Total Length
326.4 ft.
Structural Index
3
Structural Quick
3L2L
Structural Rating
320
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
320
Pipe schematic from manhole 22 0286 to 22 0287
MH: 22 0286MH: 22 0287upstream0 ft. AMH - Upstream Manhole, Survey Ends - 22 02873.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish3.1 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish44.4 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 8"52.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: YES, 8"89.1 ft. TF - Tap Factory Made, at 11 o'clock, -, within 8 inches of joint: YES, 8"109.4 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"154.7 ft. TF - Tap Factory Made, at 11 o'clock, -, within 8 inches of joint: YES, 8"158.6 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: YES, 8"223.9 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"228.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 8"288.6 ft. TF - Tap Factory Made, at 11 o'clock, -, within 8 inches of joint: YES, 8"313.7 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 8"324.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start324.4 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start326.4 ft. AMH - Downstream Manhole, Survey Begins - 22 0286326.4 ft. MWM - Water Mark, 35 %of cross sectional area326.4 ft. MWL - Water Level, 15 %of cross sectional area

Observation photos (2)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (18)

DistanceCodeObservation
237.3TF
171.7TF
0AMH22 0286
0MWM
323.3SAP
167.8TFC
217TF
98.3TF
0MWL
2SAP
274TFC
12.7TF
323.3SSS
326.4AMH22 0287
2SSS
282TF
102.5TF
37.8TF

Properties (6)

custom_field_three
AGGREGATE PROJECTING, SPALLING
custom_field_two
3
customer
1
datetime
2021-02-03T00:15:02-08:00
documentation
PRO PIPE
is_lateral_inspection
false