Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jun 22, 2018, 09:59 AM
  • B 0373_B 0372 _22062018_031051.mp4

Date
06/22/2018
W/O
712401
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00091
PipeID
P08885
Time
2:59 AM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K5703
Sewer Name
B JOINT OUTFALL B - UNIT 5A
City
TEMPLE CITY
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
10
Purpose
Routine Assessment
Project
WO_712401_TV15051_JUL2018
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
21 in.
Width
21 in.
Upstream MH
B 0373
Downstream MH
B 0372
Dir. of Survey
Downstream
Length Surveyed
330.9 ft.
Total Length
330.9 ft.
Structural Index
3
Structural Quick
3L2K
Structural Rating
325
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
325
Pipe schematic from manhole B 0373 to B 0372
MH: B 0373MH: B 0372downstream0 ft. AMH - Upstream Manhole, Survey Begins - B 03730 ft. MWM - Water Mark, 35 %of cross sectional area0 ft. MWL - Water Level, 20 %of cross sectional area2.6 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start23.3 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start157.1 ft. SAP - Surface Aggregate Projecting, from 10 to 02 o'clock, within 8 inches of joint: YES330.9 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish330.9 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish330.9 ft. MGO - General Observation - CAPPED LATERAL 9 O'CLOCK @ MH330.9 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK330.9 ft. AMH - Downstream Manhole, Survey Ends - B 0372

Observation photos (3)

  • Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.6 ft. - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    23.3 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 10 to 02 o'clock, within 8 inches of joint: YES

    157.1 ft. - Surface Aggregate Projecting, from 10 to 02 o'clock, within 8 inches of joint: YES

Observations (11)

DistanceCodeObservation
330.9SAV
330.9SSS
0AMHB 0373
2.6SAV
157.1SAP
330.9MGOCAPPED LATERAL 9 O'CLOCK @ MH
330.9MGOCONNECTION AT MH 3 O'CLOCK
0MWM
0MWL
23.3SSS
330.9AMHB 0372

Properties (6)

additional_info
SC359661
custom_field_two
3
customer
LACSD
datetime
2018-06-22T02:59:43-07:00
documentation
PROPIPE
is_lateral_inspection
false