Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Dec 9, 2020, 09:32 AM
  • H 1235_H 1234_12092020_014902.mp4

Date
12/09/2020
W/O
859970
Weather
Dry
Operator/Surveyor
M.MARTINEZ
Sewer ID
Z01181
PipeID
P17160
Time
1:32 AM
Certificate
U-115-06022794
System Owner
1
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K8238
Sewer Name
H JOINT OUTFALL H - UNIT 8K
City
COVINA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
24
Purpose
Routine Assessment
Project
WO_859970_TV22032_NOV2020
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
24 in.
Upstream MH
H 1235
Downstream MH
H 1234
Dir. of Survey
Downstream
Length Surveyed
383.8 ft.
Total Length
383.8 ft.
Structural Index
3
Structural Quick
3N2N
Structural Rating
375
O&M Index
4
O&M Quick
4N00
O&M Rating
300
Overall Index
3
Overall Quick
Overall Rating
675
Pipe schematic from manhole H 1235 to H 1234
MH: H 1235MH: H 1234downstream0 ft. MWL - Water Level, 25 %of cross sectional area0 ft. MGO - General Observation - CONNECTION AT MH, 3 O'CLOCK0 ft. MWM - Water Mark, 35 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - H 12352 ft. MGO - General Observation - MAG COAT7.1 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start7.1 ft. LL - Alignment Left, 25 %, Start7.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start16.1 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"23.8 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"71.5 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"87.3 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"110.8 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"118.4 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"166.3 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"181.7 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"220.8 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"229.1 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"283.6 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"291.5 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"338.8 ft. TFC - Tap Factory Made Capped, at 11 o'clock, -, within 8 inches of joint: YES, 8"346.3 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"383.2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish383.2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish383.2 ft. LL - Alignment Left, 25 %, Finish383.8 ft. AMH - Downstream Manhole, Survey Ends - H 1234

Observation photos (4)

  • General Observation - MAG COAT

    2 ft. - General Observation - MAG COAT

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    7.1 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Alignment Left, 25 %, Start

    7.1 ft. - Alignment Left, 25 %, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    7.1 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (26)

DistanceCodeObservation
23.8TFC
7.1SSS
181.7TFC
283.6TFC
338.8TFC
346.3TFC
229.1TF
118.4TFC
0MWL
0MGOCONNECTION AT MH, 3 O'CLOCK
0MWM
383.2SSS
7.1LL
87.3TF
220.8TFC
0AMHH 1235
383.2SAP
383.8AMHH 1234
71.5TFC
7.1SAP
291.5TF
16.1TFC
110.8TFC
2MGOMAG COAT
383.2LL
166.3TFC

Properties (6)

custom_field_three
AGGREGATE PROJECTING
custom_field_two
3
customer
1
datetime
2020-12-09T01:32:21-08:00
documentation
PRO PIPE
is_lateral_inspection
false