Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Dec 1, 2020, 07:43 AM
  • 18 0238_18 0237 _11302020_235906.mp4

Date
11/30/2020
W/O
855022
Weather
Dry
Operator/Surveyor
M.MARTINEZ
Sewer ID
Z00674
PipeID
P14066
Time
11:43 PM
Certificate
U-115-06022794
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K8225
Sewer Name
EAST IMPERIAL HIGHWAY TRUNK
City
LA MIRADA
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 18
Page No.
26
Purpose
Routine Assessment
Project
WO_855022_TV18005_OCT2020
Sewer Type
Gravity
Material
Vitrified Clay Pipe
Shape
Circular
Height
12 in.
Width
12 in.
Upstream MH
18 0238
Downstream MH
18 0237
Dir. of Survey
Downstream
Length Surveyed
276.2 ft.
Total Length
276.2 ft.
Structural Index
4
Structural Quick
4J00
Structural Rating
212
O&M Index
2
O&M Quick
2J00
O&M Rating
108
Overall Index
3
Overall Quick
Overall Rating
320
Pipe schematic from manhole 18 0238 to 18 0237
MH: 18 0238MH: 18 0237downstream0 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MGO - General Observation - CONNECTION AT MH, 3 O'CLOCK0 ft. AMH - Upstream Manhole, Survey Begins - 18 02380 ft. MWL - Water Level, 10 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start8.4 ft. FM - Fracture Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start18.5 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"68.3 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 8"118 ft. TFA - Tap Factory Made Active, at 02 o'clock, -, within 8 inches of joint: YES, 8"167.3 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"216.5 ft. TFC - Tap Factory Made Capped, at 01 o'clock, -, within 8 inches of joint: YES, 8"266.1 ft. TF - Tap Factory Made, at 01 o'clock, -, within 8 inches of joint: YES, 8"273.5 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish273.5 ft. FM - Fracture Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish276.2 ft. MGO - General Observation - CONNECTION AT MH, 9 O'CLOCK276.2 ft. AMH - Downstream Manhole, Survey Ends - 18 0237

Observation photos (2)

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Fracture Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    8.4 ft. - Fracture Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (16)

DistanceCodeObservation
8.4FM
0MWM
216.5TFC
68.3TF
2DAGS
0MGOCONNECTION AT MH, 3 O'CLOCK
266.1TF
276.2MGOCONNECTION AT MH, 9 O'CLOCK
167.3TF
273.5DAGS
276.2AMH18 0237
273.5FM
118TFA
0AMH18 0238
18.5TFC
0MWL

Properties (7)

additional_info
63007511240203
custom_field_three
FRACTURES
custom_field_two
2
customer
1
datetime
2020-11-30T23:43:37-08:00
documentation
PRO PIPE
is_lateral_inspection
false