Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Aug 13, 2020, 05:13 AM
  • H 1429_H 1428_08122020_222542.mp4

Date
08/12/2020
W/O
844678
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z01204
PipeID
P16301
Time
10:13 PM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K7954
Sewer Name
JOINT OUTFALL H - UNIT 8M
City
WEST COVINA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
31
Purpose
Routine Assessment
Project
WO_844678_TV22034_AUG2020
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
24 in.
Width
24 in.
Upstream MH
H 1429
Downstream MH
H 1428
Dir. of Survey
Downstream
Length Surveyed
301 ft.
Total Length
301 ft.
Structural Index
3
Structural Quick
3K2K
Structural Rating
295
O&M Index
2
O&M Quick
2K00
O&M Rating
118
Overall Index
2
Overall Quick
Overall Rating
413
Pipe schematic from manhole H 1429 to H 1428
MH: H 1429MH: H 1428downstream0 ft. AMH - Upstream Manhole, Survey Begins - H 14290 ft. MGO - General Observation - CONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK0 ft. MGO - General Observation - COCKROACHES IN MANHOLE0 ft. MWL - Water Level, 35 %of cross sectional area0 ft. MWM - Water Mark, 40 %of cross sectional area2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - MAG COATING THROUGHOUT230 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"298.6 ft. MGO - General Observation - CONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK298.6 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish298.6 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish298.6 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish298.6 ft. MGO - General Observation - COCKROACHES IN MANHOLE301 ft. AMH - Downstream Manhole, Survey Ends - H 1428

Observation photos (6)

  • General Observation - COCKROACHES IN MANHOLE

    0 ft. - General Observation - COCKROACHES IN MANHOLE

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COATING THROUGHOUT

    2 ft. - General Observation - MAG COATING THROUGHOUT

  • General Observation - COCKROACHES IN MANHOLE

    298.6 ft. - General Observation - COCKROACHES IN MANHOLE

Observations (16)

DistanceCodeObservation
298.6MGOCONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK
298.6SSS
0AMHH 1429
298.6SAP
0MGOCONNECTIONS IN MH AT BOTH 3 AND 9 O' CLOCK
0MGOCOCKROACHES IN MANHOLE
2SAP
0MWL
301AMHH 1428
0MWM
298.6DAGS
2DAGS
2SSS
2MGOMAG COATING THROUGHOUT
230TFC
298.6MGOCOCKROACHES IN MANHOLE

Properties (7)

additional_info
SC411744
custom_field_three
SPALLING THROUGHOUT
custom_field_two
4
customer
1
datetime
2020-08-12T22:13:46-07:00
documentation
PRO PIPE
is_lateral_inspection
false