Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Sep 15, 2020, 09:02 AM
  • 32 1176_32 1175 _09152020_022235.mp4

Date
09/15/2020
W/O
844698
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00839
PipeID
P19630
Time
2:02 AM
Certificate
U-0720-70309212
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K7990
Sewer Name
SAN FERNANDO ROAD TRUNK
City
SANTA CLARITA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 32
Page No.
09
Purpose
Routine Assessment
Project
RFIR_WO_844698_TV32021_AUG2020
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
18 in.
Upstream MH
32 1176
Downstream MH
32 1175
Dir. of Survey
Downstream
Length Surveyed
493.9 ft.
Total Length
493.9 ft.
Structural Index
3
Structural Quick
3J00
Structural Rating
165
O&M Index
2
O&M Quick
2S00
O&M Rating
196
Overall Index
2
Overall Quick
Overall Rating
361
Pipe schematic from manhole 32 1176 to 32 1175
MH: 32 1176MH: 32 1175downstream0 ft. MWL - Water Level, 5 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 32 11760 ft. MWM - Water Mark, 20 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - MAG COATING THROUGHOUT150.1 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"254.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"259.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 6"277.4 ft. MMC - Material Change, Vitrified clay pipe277.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish346.4 ft. TB - Tap Break-In, at 10 o'clock, -, within 8 inches of joint: NO, 6"347.3 ft. TB - Tap Break-In, at 02 o'clock, -, within 8 inches of joint: NO, 4"434.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"441.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"490.5 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish493.9 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK493.9 ft. AMH - Downstream Manhole, Survey Ends - 32 1175

Observation photos (4)

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAG COATING THROUGHOUT

    2 ft. - General Observation - MAG COATING THROUGHOUT

  • Material Change, Vitrified clay pipe

    277.4 ft. - Material Change, Vitrified clay pipe

Observations (18)

DistanceCodeObservation
150.1TBA
493.9MGOCONNECTION AT MH 9 O'CLOCK
2DAGS
2SAP
277.4MMC
434.3TFC
259.1TF
277.4SAP
254.9TFC
346.4TB
0MWL
347.3TB
2MGOMAG COATING THROUGHOUT
0AMH32 1176
490.5DAGS
0MWM
493.9AMH32 1175
441.1TFC

Properties (7)

additional_info
SC411882
custom_field_three
PROJECTING AGGREGATE
custom_field_two
3
customer
1
datetime
2020-09-15T02:02:48-07:00
documentation
PRO PIPE
is_lateral_inspection
false