Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jun 2, 2020, 06:01 AM
  • B 0440_B 0439_06012020_231334.mp4

Date
06/01/2020
W/O
834129
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00093
PipeID
P08952
Time
11:01 PM
Certificate
U-111-11880
System Owner
1
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K7681
Sewer Name
JOINT OUTFALL B - UNIT 5C
City
PASADENA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 16
Page No.
11
Purpose
Routine Assessment
Project
RFIR_WO_834129_TV16034_JUN2020
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
57 in.
Upstream MH
B 0440
Downstream MH
B 0439
Dir. of Survey
Downstream
Length Surveyed
353.5 ft.
Total Length
353.5 ft.
Structural Index
3
Structural Quick
3M2M
Structural Rating
350
O&M Index
2
O&M Quick
2M00
O&M Rating
140
Overall Index
2
Overall Quick
Overall Rating
490
Pipe schematic from manhole B 0440 to B 0439
MH: B 0440MH: B 0439downstream0 ft. MGO - General Observation - ROACHES @ MANHOLE0 ft. MWM - Water Mark, 30 %of cross sectional area0 ft. MGO - General Observation - CONN @ MH 3 O'CLOCK/OPEN0 ft. MWL - Water Level, 25 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - B 04402 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. MGO - General Observation - 45% MAG COAT2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start351.9 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish351.9 ft. MGO - General Observation - ROACHES @ MANHOLE351.9 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish351.9 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish353 ft. MGO - General Observation - CONN @ MH 7 O'CLOCK/CAPPED353.5 ft. AMH - Downstream Manhole, Survey Ends - B 0439

Observation photos (5)

  • General Observation - ROACHES @ MANHOLE

    0 ft. - General Observation - ROACHES @ MANHOLE

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

  • General Observation - ROACHES @ MANHOLE

    351.9 ft. - General Observation - ROACHES @ MANHOLE

Observations (15)

DistanceCodeObservation
0MGOROACHES @ MANHOLE
0MWM
353.5AMHB 0439
0MGOCONN @ MH 3 O'CLOCK/OPEN
351.9DAGS
2SSS
2SAP
353MGOCONN @ MH 7 O'CLOCK/CAPPED
2MGO45% MAG COAT
2DAGS
351.9MGOROACHES @ MANHOLE
351.9SSS
0MWL
0AMHB 0440
351.9SAP

Properties (7)

additional_info
SC411273
custom_field_three
SPALLING/PROJECTING AGGREGATE
custom_field_two
2
customer
1
datetime
2020-06-01T23:01:16-07:00
documentation
PRO PIPE
is_lateral_inspection
false