Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 1, 2020, 10:07 AM
  • 01 0425_01 0424_04012020_031820.mp4

Date
04/01/2020
W/O
818388
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00208
PipeID
P00906
Time
3:07 AM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K7498
Sewer Name
01 HOLMES-WILLOWBROOK TRUNK
City
LOS ANGELES
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 01
Page No.
13
Purpose
Routine Assessment
Project
RFIR_WO_818388_TV01030_MAR2020
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
18 in.
Width
18 in.
Upstream MH
01 0425
Downstream MH
01 0424
Dir. of Survey
Downstream
Length Surveyed
238.4 ft.
Total Length
238.4 ft.
Structural Index
3
Structural Quick
3121
Structural Rating
5
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
5
Pipe schematic from manhole 01 0425 to 01 0424
MH: 01 0425MH: 01 0424downstream0 ft. MWL - Water Level, 10 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 01 04250 ft. MWM - Water Mark, 25 %of cross sectional area2.1 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start19.9 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"26.2 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"38.9 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"63.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"68 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"88.6 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 6"90.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"97.1 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"109.2 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: NO, 6"147.2 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"162.5 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"167.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"195 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"238.4 ft. AMH - Downstream Manhole, Survey Ends - 01 0424238.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish238.4 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

Observation photos (2)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.1 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.1 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (21)

DistanceCodeObservation
26.2TF
88.6TF
97.1TFC
68TFC
2.1SSS
19.9TF
109.2TF
147.2TFC
238.4AMH01 0424
0MWL
38.9TFC
2.1SAP
195TFC
63.3TFC
0AMH01 0425
167.6TFC
90.6TFC
238.4SAP
162.5TFC
0MWM
238.4SSS

Properties (6)

additional_info
SC411105
custom_field_two
3
customer
LACSD
datetime
2020-04-01T03:07:44-07:00
documentation
PROPIPE
is_lateral_inspection
false