Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Feb 19, 2020, 09:21 AM
  • A 0522_A 0521 _02192020_024958.mp4

Date
02/19/2020
W/O
813372
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00315
PipeID
P07758
Time
1:21 AM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K7459
Sewer Name
A JOA-1A DISTRICT 5 INTERCEPTOR
City
TORRANCE
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 05
Page No.
20
Purpose
Routine Assessment
Project
RFIR_WO_813372_TV05119_FEB2020
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
54 in.
Width
54 in.
Upstream MH
A 0522
Downstream MH
A 0521
Dir. of Survey
Downstream
Length Surveyed
591.2 ft.
Total Length
591.2 ft.
Structural Index
3
Structural Quick
3V00
Structural Rating
351
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
351
Pipe schematic from manhole A 0522 to A 0521
MH: A 0522MH: A 0521downstream0 ft. MWM - Water Mark, 35 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - A 05220 ft. MWL - Water Level, 25 %of cross sectional area4.3 ft. MGO - General Observation - MAG COAT4.3 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start30 ft. MGO - General Observation - ALIGNMENT RIGHT 10% START45.5 ft. MGO - General Observation - REINFORCEMENT PROJECTING - 2 O'CLOCK65 ft. MGO - General Observation - HOLE - POSSIBLE SOIL @ 3 O'CLOCK340.3 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 6" - ACTIVE341.7 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: NO, 6" - ACTIVE589 ft. MGO - General Observation - ALIGNMENT RIGHT 10% FINISH590.7 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish591.2 ft. AMH - Downstream Manhole, Survey Ends - A 0521

Observation photos (1)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    4.3 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (13)

DistanceCodeObservation
4.3MGOMAG COAT
590.7SAP
341.7TFACTIVE
0MWM
4.3SAP
0AMHA 0522
340.3TFACTIVE
45.5MGOREINFORCEMENT PROJECTING - 2 O'CLOCK
591.2AMHA 0521
0MWL
30MGOALIGNMENT RIGHT 10% START
589MGOALIGNMENT RIGHT 10% FINISH
65MGOHOLE - POSSIBLE SOIL @ 3 O'CLOCK

Properties (7)

additional_info
SC398864
custom_field_three
AGGREGATE AND REBAR PROJECTING, HOLE - WITH SOIL?
custom_field_two
1
customer
LACSD
datetime
2020-02-19T01:21:59-08:00
documentation
PROPIPE
is_lateral_inspection
false