Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Dec 9, 2016, 02:56 PM
  • 30 0180_30 0372 _09122016_065650.mp4

Date
12/09/2016
W/O
597389
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00860
PipeID
P22430
Time
6:56 AM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K3846
Sewer Name
30 EL PORTO TRUNK
City
MANHATTEN BEACH
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 30
Page No.
02
Purpose
Routine Assessment
Project
WO_597389_TV30002_OCT2016
Sewer Type
Gravity
Material
Vitrified Clay Pipe
Shape
Circular
Height
10 in.
Width
10 in.
Upstream MH
30 0180
Downstream MH
30 0372
Dir. of Survey
Downstream
Length Surveyed
68.2 ft.
Total Length
68.2 ft.
Structural Index
3
Structural Quick
3600
Structural Rating
18
O&M Index
2
O&M Quick
2100
O&M Rating
2
Overall Index
3
Overall Quick
Overall Rating
20
Pipe schematic from manhole 30 0180 to 30 0372
MH: 30 0180MH: 30 0372downstream0 ft. MWM - Water Mark, 20 %of cross sectional area0 ft. MWL - Water Level, 10 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 30 01800 ft. MGO - General Observation - CONNECTION AT THE MH 9 O'CLOCK3 ft. CM - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES3 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, at 05 o'clock, , within 8 inches of joint: YES6.1 ft. CM - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES50 ft. CM - Crack Multiple, from 02 to 04 o'clock, within 8 inches of joint: YES53.2 ft. CM - Crack Multiple, from 09 to 04 o'clock, within 8 inches of joint: YES56.2 ft. CM - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start65 ft. CM - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish68.2 ft. AMH - Downstream Manhole, Survey Ends - 30 037268.2 ft. MGO - General Observation - CONNECTION AT THE MH 9 O'CLOCK

Observation photos (7)

  • Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES

    3 ft. - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES

  • Deposits Attached Grease, 5 %of cross sectional area, at 05 o'clock,  , within 8 inches of joint: YES

    3 ft. - Deposits Attached Grease, 5 %of cross sectional area, at 05 o'clock, , within 8 inches of joint: YES

  • Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES

    6.1 ft. - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES

  • Crack Multiple, from 02 to 04 o'clock, within 8 inches of joint: YES

    50 ft. - Crack Multiple, from 02 to 04 o'clock, within 8 inches of joint: YES

  • Crack Multiple, from 09 to 04 o'clock, within 8 inches of joint: YES

    53.2 ft. - Crack Multiple, from 09 to 04 o'clock, within 8 inches of joint: YES

  • Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    56.2 ft. - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

    65 ft. - Crack Multiple, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

Observations (13)

DistanceCodeObservation
0MWM
56.2CM
53.2CM
65CM
3CM
6.1CM
0MWL
0AMH30 0180
3DAGS
68.2AMH30 0372
68.2MGOCONNECTION AT THE MH 9 O'CLOCK
0MGOCONNECTION AT THE MH 9 O'CLOCK
50CM

Properties (6)

additional_info
SC304597
custom_field_two
3
customer
LACSD
datetime
2016-12-09T06:56:14-08:00
documentation
PROPIPE
is_lateral_inspection
false