Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jul 30, 2019, 05:15 PM
  • H 0698_H 0697_07302019_101740.mp4

Date
07/30/2019
W/O
766531
Weather
Dry
Operator/Surveyor
J. VARGAS
Sewer ID
Z00941
PipeID
P11105
Time
10:15 AM
Certificate
U-209-8149
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K6771
Sewer Name
H JOINT OUTFALL H - UNIT 9B
City
WHITTIER
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 18
Page No.
01
Purpose
Routine Assessment
Project
WO_766531_TV18175_MAY2019
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
25 in.
Width
25 in.
Upstream MH
H 0698
Downstream MH
H 0697
Dir. of Survey
Downstream
Length Surveyed
171.1 ft.
Total Length
171 ft.
Structural Index
3
Structural Quick
3F2F
Structural Rating
170
O&M Index
2
O&M Quick
2F00
O&M Rating
68
Overall Index
2
Overall Quick
Overall Rating
238
Pipe schematic from manhole H 0698 to H 0697
MH: H 0698MH: H 0697downstream0 ft. MWM - Water Mark, 40 %of cross sectional area0 ft. MGO - General Observation - REVERSAL0 ft. MWL - Water Level, 30 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - H 06982.1 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2.1 ft. MGO - General Observation - MAGNEZIUM H.O COATING THROUGHOUT REACH2.1 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start171.1 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish171.1 ft. MSA - Survey Abandoned - MATCHED FOOTAGE171.1 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish171.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish

Observation photos (4)

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.1 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.1 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • General Observation - MAGNEZIUM H.O COATING THROUGHOUT REACH

    2.1 ft. - General Observation - MAGNEZIUM H.O COATING THROUGHOUT REACH

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2.1 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

Observations (12)

DistanceCodeObservation
0MWM
171.1DAGS
2.1SSS
2.1SAP
171.1MSAMATCHED FOOTAGE
0MGOREVERSAL
2.1MGOMAGNEZIUM H.O COATING THROUGHOUT REACH
171.1SSS
2.1DAGS
171.1SAP
0MWL
0AMHH 0698

Properties (6)

additional_info
SC378277
custom_field_two
2
customer
LACSD
datetime
2019-07-30T10:15:05-07:00
documentation
PROPIPE
is_lateral_inspection
false