Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0May 3, 2019, 08:28 AM
  • 10_1_1_03052019_014702.mp4

Date
05/03/2019
W/O
761820
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00598
PipeID
P12256
Time
1:28 AM
Certificate
U-111-11880
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K6522
Sewer Name
15 BALDWIN PARK TRUNK
City
INDUSTRY
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
29
Purpose
Routine Assessment
Project
WO_761820_TV15019_APR2019
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
30 in.
Width
30 in.
Upstream MH
15 0330
Downstream MH
15 0329
Dir. of Survey
Downstream
Length Surveyed
417.8 ft.
Total Length
417.8 ft.
Structural Index
3
Structural Quick
3222
Structural Rating
10
O&M Index
3
O&M Quick
4122
O&M Rating
8
Overall Index
3
Overall Quick
Overall Rating
18
Pipe schematic from manhole 15 0330 to 15 0329
MH: 15 0330MH: 15 0329downstream0 ft. MWL - Water Level, 25 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 15 03300 ft. MWM - Water Mark, 50 %of cross sectional area2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start59.3 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"67.2 ft. TBA - Tap Break-In Active, at 10 o'clock, -, within 8 inches of joint: NO, 6"155.7 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"162.9 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"259.6 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"267.8 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"355.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"364.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"415.2 ft. SAP - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish415.2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish415.2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Finish417.8 ft. AMH - Downstream Manhole, Survey Ends - 15 0329

Observation photos (3)

  • Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: YES, Start

Observations (18)

DistanceCodeObservation
415.2SAP
155.7TFC
59.3TFC
0MWL
2SAP
415.2SSS
0AMH15 0330
162.9TFC
67.2TBA
355.4TFC
364.1TFC
2SSS
267.8TFC
415.2DAGS
2DAGS
259.6TFC
0MWM
417.8AMH15 0329

Properties (6)

additional_info
SC366242
custom_field_two
3
customer
LACSD
datetime
2019-05-03T01:28:53-07:00
documentation
PRO PIPE
is_lateral_inspection
false