Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 26, 2019, 03:00 PM
  • 15 0232A_15 0232_06112019_020652.mp4

Date
04/26/2019
W/O
766400
Weather
Dry
Operator/Surveyor
J. VARGAS
Sewer ID
Z00627
PipeID
P12154
Time
8:00 AM
Certificate
U-209-8149
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K6603
Sewer Name
15 SAN JOSE CREEK TRUNK
City
INDUSTRY
Loc. details
Easement/Right of Way
Location Code
D
Use of Sewer
Sanitary Sewer
District
District 15
Page No.
33
Purpose
Routine Assessment
Project
WO_766400_TV15133_MAY2019
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
36 in.
Width
36 in.
Upstream MH
15 0232A
Downstream MH
15 0232
Dir. of Survey
Downstream
Length Surveyed
182.6 ft.
Total Length
182.6 ft.
Structural Index
3
Structural Quick
5131
Structural Rating
10
O&M Index
2
O&M Quick
2111
O&M Rating
3
Overall Index
3
Overall Quick
Overall Rating
13
Pipe schematic from manhole 15 0232A to 15 0232
MH: 15 0232AMH: 15 0232downstream0 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK ACTIVE0 ft. AMH - Upstream Manhole, Survey Begins - 15 0232A0 ft. VC - Vermin Cockroach0 ft. MWL - Water Level, 30 %of cross sectional area0 ft. MWM - Water Mark, 40 %of cross sectional area2 ft. SRV - Surface Reinforcement Visible, from 09 to 12 o'clock, within 8 inches of joint: YES2.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2.4 ft. MGO - General Observation - MAG COAT THROUGHOUT REACH2.4 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2.4 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start101.8 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"179.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish179.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish179.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish182.6 ft. AMH - Downstream Manhole, Survey Ends - 15 0232

Observation photos (3)

  • General Observation - MAG COAT THROUGHOUT REACH

    2.4 ft. - General Observation - MAG COAT THROUGHOUT REACH

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.4 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2.4 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

Observations (15)

DistanceCodeObservation
0MGOCONNECTION AT MH 9 O'CLOCK ACTIVE
179.8SAP
2.4SAP
2.4MGOMAG COAT THROUGHOUT REACH
179.8SSS
101.8TFC
2.4SSS
0AMH15 0232A
0VC
0MWL
182.6AMH15 0232
179.8DAGS
0MWM
2.4DAGS
2SRV

Properties (6)

additional_info
SC377527
custom_field_two
2
customer
LACSD
datetime
2019-04-26T08:00:42-07:00
documentation
PRO PIPE
is_lateral_inspection
false