Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Dec 24, 2015, 08:00 AM
  • 14 0433A_14 0433_24122015_000114.mp4

Date
12/24/2015
W/O
541758
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00578
PipeID
P18519
Time
12:00 AM
Certificate
U-111-11880
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K3058
Sewer Name
14 TRUNK "B"
City
LANCASTER
Loc. details
Main Highway - Suburban/Rural
Location Code
B
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
05
Purpose
Routine Assessment
Project
WO_541758_TV14019_DEC2015
Sewer Type
GRAVITY
Material
NRCP
Shape
Circular
Height
15 in.
Upstream MH
14 0433A
Downstream MH
14 0433
Dir. of Survey
Downstream
Length Surveyed
93.6 ft.
Total Length
93.6 ft.
Structural Index
3
Structural Quick
3C2C
Structural Rating
90
O&M Index
2
O&M Quick
2C00
O&M Rating
36
Overall Index
2
Overall Quick
Overall Rating
126
Pipe schematic from manhole 14 0433A to 14 0433
MH: 14 0433AMH: 14 0433downstream0 ft. MWL - Water Level, 20 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 0433A0 ft. MWM - Water Mark, 40 %of cross sectional area0 ft. MGO - General Observation - ACTIVE CONNECTION AT MH 9 O'CLOCK2 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start2 ft. SAV - Surface Aggregate Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"32.2 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"55.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"81.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"91.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish91.8 ft. SSS - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish91.8 ft. SAV - Surface Aggregate Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Finish93.6 ft. AMH - Downstream Manhole, Survey Ends - 14 0433

Observation photos (3)

  • Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Surface Aggregate Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Visible, from 09 to 03 o'clock, within 8 inches of joint: YES, Start

Observations (15)

DistanceCodeObservation
93.6AMH14 0433
0MWL
0AMH14 0433A
2SSS
2DAGS
8TFC
91.8DAGS
32.2TFC
0MWM
91.8SSS
0MGOACTIVE CONNECTION AT MH 9 O'CLOCK
2SAV
91.8SAV
81.1TFC
55.4TFC

Properties (6)

additional_info
SC204197
custom_field_two
2
customer
LACSD
datetime
2015-12-24T00:00:55-08:00
documentation
PRO PIPE
is_lateral_inspection
false