Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0May 17, 2018, 08:19 PM
  • B 0006_B 0005_17052018_134303.mp4

Date
05/17/2018
W/O
701684
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00072
PipeID
P08516
Time
1:19 PM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K5672
Sewer Name
B JOINT OUTFALL B - UNIT 1A
City
CARSON
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 08
Page No.
16
Purpose
Routine Assessment
Project
WO_701684_TV30071_MAY2018
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
144 in.
Width
144 in.
Upstream MH
B 0006
Downstream MH
B 0005
Dir. of Survey
Downstream
Length Surveyed
638.4 ft.
Total Length
638.4 ft.
Structural Index
4
Structural Quick
5X3X
Structural Rating
1011
O&M Index
2
O&M Quick
2100
O&M Rating
2
Overall Index
4
Overall Quick
Overall Rating
1013
Pipe schematic from manhole B 0006 to B 0005
MH: B 0006MH: B 0005downstream0 ft. MWL - Water Level, 15 %of cross sectional area0 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - B 00066.1 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start6.1 ft. SRV - Surface Reinforcement Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start6.1 ft. MGO - General Observation - MAG COAT80.7 ft. OBP - Obstacles External Pipe or Cable, 10 %of cross sectional area, from 10 to 02 o'clock188.6 ft. SRP - Surface Reinforcement Projecting, from 01 to 02 o'clock, within 8 inches of joint: YES638.4 ft. SRV - Surface Reinforcement Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish638.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish638.4 ft. MGO - General Observation - CONNECTION AT MH 3 O'CLOCK638.4 ft. AMH - Downstream Manhole, Survey Ends - B 0005

Observation photos (4)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    6.1 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Reinforcement Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    6.1 ft. - Surface Reinforcement Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Obstacles External Pipe or Cable, 10 %of cross sectional area, from 10 to 02 o'clock

    80.7 ft. - Obstacles External Pipe or Cable, 10 %of cross sectional area, from 10 to 02 o'clock

  • Surface Reinforcement Projecting, from 01 to 02 o'clock, within 8 inches of joint: YES

    188.6 ft. - Surface Reinforcement Projecting, from 01 to 02 o'clock, within 8 inches of joint: YES

Observations (12)

DistanceCodeObservation
0MWL
638.4SRV
638.4SAP
638.4MGOCONNECTION AT MH 3 O'CLOCK
6.1SAP
6.1SRV
638.4AMHB 0005
0MWM
0AMHB 0006
80.7OBP
6.1MGOMAG COAT
188.6SRP

Properties (6)

additional_info
SC359330
custom_field_two
2
customer
LACSD
datetime
2018-05-17T13:19:15-07:00
is_lateral_inspection
false
year_laid
36930