Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Mar 15, 2019, 07:46 AM
  • 05 0927_05 0926 _03152019_010237.mp4

Date
03/15/2019
W/O
755855
Weather
Dry
Operator/Surveyor
E.RUIZ
Sewer ID
Z00547
PipeID
P06159
Time
12:46 AM
Certificate
U-715-07000753
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K6476
Sewer Name
05 120TH STREET EXTENSION TRUNK
City
HAWTHORNE
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 05
Page No.
12
Purpose
Routine Assessment
Project
RFIR_WO_755855_TV05175_MAR2019
Sewer Type
Gravity
Material
NRCP
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
05 0927
Downstream MH
05 0926
Dir. of Survey
Downstream
Length Surveyed
339.6 ft.
Total Length
339.6 ft.
Structural Index
3
Structural Quick
3200
Structural Rating
6
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
6
Pipe schematic from manhole 05 0927 to 05 0926
MH: 05 0927MH: 05 0926downstream0 ft. MWL - Water Level, 10 %of cross sectional area0 ft. MWM - Water Mark, 20 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 05 09273.7 ft. MGO - General Observation - MAGNEZIUM H.O COATING start3.7 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start13.2 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8"13.2 ft. SAP - Surface Aggregate Projecting, from 07 to 05 o'clock, within 8 inches of joint: YES, Change68.2 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8"120.3 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8"172.2 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8"224 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8", 8"276.1 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8", 8"327.8 ft. TFC - Tap Factory Made Capped, at 12 o'clock, -, within 8 inches of joint: YES, 8"336.2 ft. SAP - Surface Aggregate Projecting, from 07 to 05 o'clock, within 8 inches of joint: YES, Finish336.2 ft. MGO - General Observation - MAGNEZIUM H.O COATING finish339.6 ft. MGO - General Observation - SERVICE CONNECTION AT 3 O' CLOCK AT MH339.6 ft. AMH - Downstream Manhole, Survey Ends - 05 0926

Observation photos (1)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    3.7 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (17)

DistanceCodeObservation
336.2SAP
0MWL
13.2TFC
3.7MGOMAGNEZIUM H.O COATING start
120.3TFC
327.8TFC
336.2MGOMAGNEZIUM H.O COATING finish
339.6MGOSERVICE CONNECTION AT 3 O' CLOCK AT MH
172.2TFC
276.1TFC
68.2TFC
0MWM
3.7SAP
224TFC
0AMH05 0927
339.6AMH05 0926
13.2SAP

Properties (5)

custom_field_two
2
customer
LACSD
datetime
2019-03-15T00:46:26-07:00
documentation
PROPIPE
is_lateral_inspection
false