Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Nov 16, 2018, 04:30 PM
  • 22 0742_22 0741_11162018_092033.mp4

Date
11/16/2018
W/O
0735393
Weather
Dry
Operator/Surveyor
FRANKLIN
Sewer ID
Z00821
PipeID
P17098
Time
8:30 AM
Certificate
U-415-06024039
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
G7855
Sewer Name
22 PUDDINGSTONE TRUNK, SECTS 1&2
City
SAN DIMAS
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 22
Page No.
22
Purpose
Capital Improvement Program Assesment
Project
20181116DF_PUDDINGSTONE_TRUNK_SECTS_1_2
Material
NRCP
Shape
Circular
Height
15 in.
Upstream MH
22 0742
Downstream MH
22 0741
Dir. of Survey
Downstream
Length Surveyed
273 ft.
Total Length
273 ft.
Structural Index
3
Structural Quick
3221
Structural Rating
8
O&M Index
2
O&M Quick
2200
O&M Rating
4
Overall Index
2
Overall Quick
Overall Rating
12
Pipe schematic from manhole 22 0742 to 22 0741
MH: 22 0742MH: 22 0741downstream0 ft. AMH - Upstream Manhole, Survey Begins - 8:39 AM0.1 ft. MWL - Water Level, 15 %of cross sectional area0.1 ft. MWM - Water Mark, 20 %of cross sectional area2 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. SZ - Surface Other, from 08 to 04 o'clock, within 8 inches of joint: YES, Start - 60% MAG2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start39 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4", 4" - Unkown43.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown51.3 ft. MGP - General Photograph - PEELING AND FLAKING63.3 ft. MGP - General Photograph87.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown91.3 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4" - Open123 ft. MGP - General Photograph139.2 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4" - Unkown143.7 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown183.3 ft. TFD - Tap Factory Made Defective, at 02 o'clock, -, within 8 inches of joint: YES, 4" - -LATERAL187.7 ft. TFD - Tap Factory Made Defective, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown/90% GREASE-LATERAL236.1 ft. TF - Tap Factory Made, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown240.5 ft. TF - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4" - Unkown244.4 ft. TB - Tap Break-In, at 09 o'clock, -, within 8 inches of joint: YES, 4" - Open268.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish268.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish268.8 ft. SZ - Surface Other, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish - 60% MAG268.8 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish272.3 ft. MGO - General Observation - Peeling & Flaking Throughout The Reach272.3 ft. MGO - General Observation - Conn. @ Mh, 5 O' Clock. Active273 ft. MGO - General Observation - Grease Throughout The Reach (5%)273 ft. AMH - Downstream Manhole, Survey Ends - 9:51 AM

Observation photos (11)

  • Upstream Manhole, Survey Begins - 8:39 AM

    0 ft. - Upstream Manhole, Survey Begins - 8:39 AM

  • Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Other, from 08 to 04 o'clock, within 8 inches of joint: YES, Start - 60% MAG

    2 ft. - Surface Other, from 08 to 04 o'clock, within 8 inches of joint: YES, Start - 60% MAG

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4", 4" - Unkown

    39 ft. - Tap Factory Made, at 02 o'clock, -, within 8 inches of joint: YES, 4", 4" - Unkown

  • General Photograph - PEELING AND FLAKING

    51.3 ft. - General Photograph - PEELING AND FLAKING

  • General Photograph

    63.3 ft. - General Photograph

  • General Photograph

    123 ft. - General Photograph

  • Tap Factory Made Defective, at 02 o'clock, -, within 8 inches of joint: YES, 4" - -LATERAL

    183.3 ft. - Tap Factory Made Defective, at 02 o'clock, -, within 8 inches of joint: YES, 4" - -LATERAL

  • Tap Factory Made Defective, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown/90% GREASE-LATERAL

    187.7 ft. - Tap Factory Made Defective, at 10 o'clock, -, within 8 inches of joint: YES, 4" - Unkown/90% GREASE-LATERAL

Observations (29)

DistanceCodeObservation
91.3TFOpen
39TFUnkown
51.3MGPPEELING AND FLAKING
0.1MWL
0.1MWM
2SAV
0AMH8:39 AM
273MGOGrease Throughout The Reach (5%)
123MGP
268.8SAP
2SAP
187.7TFDUnkown/90% GREASE-LATERAL
2SZ60% MAG
268.8SSS
183.3TFD-LATERAL
273AMH9:51 AM
244.4TBOpen
63.3MGP
236.1TFUnkown
240.5TFUnkown
268.8SZ60% MAG
43.1TFUnkown
272.3MGOPeeling & Flaking Throughout The Reach
139.2TFUnkown
2SSS
272.3MGOConn. @ Mh, 5 O' Clock. Active
268.8SAV
143.7TFUnkown
87.1TFUnkown

Properties (5)

custom_field_two
2
customer
LACSD
datetime
2018-11-16T08:30:23-08:00
documentation
FRANKLIN, CASTILLO, RUVALCABA
is_lateral_inspection
false