05 0424_05 0423_11142018_045022.mp4
2 ft. - General Observation - MAG COAT 98% START 9:00 TO 3:00
2 ft. - Surface Spalling, from 09 to 03 o'clock, within 8 inches of joint: YES, Start - FLAKING PEELING CONCRETE
58.7 ft. - Surface Spalling, from 09 to 12 o'clock, within 8 inches of joint: NO - PEELING CONCRETE UNDER MAG COAT
69.8 ft. - Surface Spalling, from 11 to 01 o'clock, within 8 inches of joint: NO - FLAKING CONCRETE
217.8 ft. - Tap Break-In Intruding, at 12 o'clock, -, -, within 8 inches of joint: NO, 6", 2" - Active
268.6 ft. - Water Mark, 50 %of cross sectional area
288.7 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 03 to 09 o'clock, , within 8 inches of joint: NO
| Distance | Code | Observation |
|---|---|---|
| 69.8 | SSS | FLAKING CONCRETE |
| 217.8 | TBI | Active |
| 355.2 | MGO | 98% MAG COAT FINISH |
| 0 | MWL | — |
| 288.7 | DAGS | — |
| 0 | MWM | — |
| 355.2 | SSS | FLAKING PEELING CONCRETE |
| 2 | MGO | MAG COAT 98% START 9:00 TO 3:00 |
| 12.6 | TF | Open |
| 355.7 | AMH | 5:20AM |
| 58.7 | SSS | PEELING CONCRETE UNDER MAG COAT |
| 0 | AMH | 4:55AM |
| 268.6 | MWM | — |
| 2 | SSS | FLAKING PEELING CONCRETE |