Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0May 9, 2018, 08:34 AM
  • 18 0731_18 0730 _09052018_013938.mp4

Date
05/09/2018
W/O
701388
Weather
Dry
Operator/Surveyor
E.RUIZ
Sewer ID
Z00706
PipeID
P14584
Time
1:34 AM
Certificate
U-715-07000753
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K5315
Sewer Name
18 SO WHITTIER OUTFALL TR, SECTS 1,2,3,&4
City
WHITTIER
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 18
Page No.
26
Purpose
Routine Assessment
Project
WO_701388_TV18103_MAY2018
Sewer Type
Gravity
Material
Reinforced Concrete Pipe
Shape
Circular
Height
33 in.
Width
33 in.
Upstream MH
18 0731
Downstream MH
18 0730
Dir. of Survey
Downstream
Length Surveyed
65.4 ft.
Total Length
65.4 ft.
Structural Index
3
Structural Quick
3200
Structural Rating
6
O&M Index
4
O&M Quick
4100
O&M Rating
4
Overall Index
3
Overall Quick
Overall Rating
10
Pipe schematic from manhole 18 0731 to 18 0730
MH: 18 0731MH: 18 0730downstream0 ft. AMH - Upstream Manhole, Survey Begins - 18 07310 ft. MGO - General Observation - CAPPED CONNECTION AT 3 O' CLOCK AT MH0 ft. MWL - Water Level, 35 %of cross sectional area0 ft. MWM - Water Mark, 50 %of cross sectional area6.9 ft. MGO - General Observation - MAGNEZIUM H.O COATING start15.8 ft. SAP - Surface Aggregate Projecting, from 11 to 12 o'clock, within 8 inches of joint: YES55.9 ft. SAP - Surface Aggregate Projecting, from 12 to 01 o'clock, within 8 inches of joint: YES61.1 ft. MGO - General Observation - MAGNEZIUM H.O COATING finish65.4 ft. AMH - Downstream Manhole, Survey Ends - 18 073065.4 ft. MGO - General Observation - CAPPED CONNECTION AT 3 O' CLOCK AT MH

Observation photos (3)

  • General Observation - MAGNEZIUM H.O COATING start

    6.9 ft. - General Observation - MAGNEZIUM H.O COATING start

  • Surface Aggregate Projecting, from 11 to 12 o'clock, within 8 inches of joint: YES

    15.8 ft. - Surface Aggregate Projecting, from 11 to 12 o'clock, within 8 inches of joint: YES

  • Surface Aggregate Projecting, from 12 to 01 o'clock, within 8 inches of joint: YES

    55.9 ft. - Surface Aggregate Projecting, from 12 to 01 o'clock, within 8 inches of joint: YES

Observations (10)

DistanceCodeObservation
65.4AMH18 0730
61.1MGOMAGNEZIUM H.O COATING finish
0AMH18 0731
55.9SAP
0MGOCAPPED CONNECTION AT 3 O' CLOCK AT MH
65.4MGOCAPPED CONNECTION AT 3 O' CLOCK AT MH
15.8SAP
6.9MGOMAGNEZIUM H.O COATING start
0MWL
0MWM

Properties (3)

custom_field_two
3
customer
LACSD
datetime
2018-05-09T01:34:37-07:00