Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Apr 28, 2016, 06:43 AM
  • C 0358_C 0357_27042016_234353.mp4

Date
04/27/2016
W/O
563382
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00140
PipeID
P09821
Time
11:43 PM
Certificate
U-111-11880
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K3332
Sewer Name
C JOINT OUTFALL C - UNIT 8B
City
LONG BEACH
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 19
Page No.
09
Purpose
Routine Assessment
Project
WO_563382_TV19020_APRIL2016
Sewer Type
GRAVITY
Material
Reinforced Concrete Pipe
Shape
Circular
Height
39 in.
Upstream MH
C 0358
Downstream MH
C 0357
Dir. of Survey
Downstream
Length Surveyed
792.8 ft.
Total Length
792.8 ft.
Structural Index
3
Structural Quick
3_2_
Structural Rating
790
O&M Index
2
O&M Quick
2_00
O&M Rating
316
Overall Index
2
Overall Quick
Overall Rating
1106
Pipe schematic from manhole C 0358 to C 0357
MH: C 0358MH: C 0357downstream0 ft. AMH - Upstream Manhole, Survey Begins - C 03580 ft. MWM - Water Mark, 40 %of cross sectional area0 ft. MWL - Water Level, 25 %of cross sectional area2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start2 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start792.8 ft. AMH - Downstream Manhole, Survey Ends - C 0357792.8 ft. SSS - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish792.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish792.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish

Observation photos (3)

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

  • Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Spalling, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (10)

DistanceCodeObservation
792.8AMHC 0357
792.8SSS
792.8SAP
2DAGS
0AMHC 0358
0MWM
2SSS
0MWL
2SAP
792.8DAGS

Properties (4)

additional_info
SC305606
custom_field_two
2
customer
LACSD
datetime