Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jan 22, 2018, 11:47 AM
  • J 0048_J 0046 _22012018_040939.mp4

Date
01/22/2018
W/O
679391
Weather
Dry
Operator/Surveyor
B.FUGATE
Sewer ID
Z00062
PipeID
P11625
Time
3:47 AM
Certificate
U-508-7069
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K5414
Sewer Name
J JOINT OUTFALL J - UNIT 2C
City
LOMITA
Loc. details
Main Highway - Urban
Location Code
A
Use of Sewer
Sanitary Sewer
District
District 05
Page No.
32
Purpose
Routine Assessment
Project
WO_679391_TV05287_JAN2018
Material
Reinforced Concrete Pipe
Shape
Circular
Height
42 in.
Width
42 in.
Upstream MH
J 0048
Downstream MH
J 0046
Dir. of Survey
Downstream
Length Surveyed
734.8 ft.
Total Length
734.8 ft.
Structural Index
3
Structural Quick
513]
Structural Rating
455
O&M Index
0
O&M Quick
0000
O&M Rating
0
Overall Index
3
Overall Quick
Overall Rating
455
Pipe schematic from manhole J 0048 to J 0046
MH: J 0048MH: J 0046downstream0 ft. AMH - Upstream Manhole, Survey Begins - J 00480 ft. MWM - Water Mark, 25 %of cross sectional area0 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK0 ft. MWL - Water Level, 10 %of cross sectional area2.1 ft. MGO - General Observation - MAG COAT2.1 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start109 ft. SRV - Surface Reinforcement Visible, at 12 o'clock, within 8 inches of joint: YES109 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES180.4 ft. SAP - Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: YES365.9 ft. SAP - Surface Aggregate Projecting, from 03 to 04 o'clock, within 8 inches of joint: YES504.3 ft. SAP - Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: NO512.9 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start512.9 ft. SAV - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish734.8 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish734.8 ft. AMH - Downstream Manhole, Survey Ends - J 0046734.8 ft. MGO - General Observation - CONNECTION AT MH 9 O'CLOCK

Observation photos (7)

  • Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2.1 ft. - Surface Aggregate Visible, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Surface Reinforcement Visible, at 12 o'clock, within 8 inches of joint: YES

    109 ft. - Surface Reinforcement Visible, at 12 o'clock, within 8 inches of joint: YES

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES

    109 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES

  • Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: YES

    180.4 ft. - Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: YES

  • Surface Aggregate Projecting, from 03 to 04 o'clock, within 8 inches of joint: YES

    365.9 ft. - Surface Aggregate Projecting, from 03 to 04 o'clock, within 8 inches of joint: YES

  • Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: NO

    504.3 ft. - Surface Aggregate Projecting, from 02 to 03 o'clock, within 8 inches of joint: NO

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    512.9 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

Observations (16)

DistanceCodeObservation
0AMHJ 0048
0MWM
504.3SAP
734.8SAP
2.1MGOMAG COAT
512.9SAP
734.8AMHJ 0046
734.8MGOCONNECTION AT MH 9 O'CLOCK
180.4SAP
512.9SAV
109SRV
2.1SAV
365.9SAP
109SAP
0MGOCONNECTION AT MH 9 O'CLOCK
0MWL

Properties (5)

additional_info
SC346798
custom_field_two
2
customer
LACSD
datetime
2018-01-22T03:47:33-08:00
sewer_category
Gravity