Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Jan 23, 2017, 12:09 PM
  • 14 0476_14 0475 _01232017_041551.mp4

Date
01/23/2017
W/O
618867
Weather
Dry
Operator/Surveyor
S. LOPEZ
Sewer ID
Z00580
PipeID
P18565
Time
4:09 AM
Certificate
U-111-11880
System Owner
LACSD
Date Cleaned
Pre-Cleaning
No Pre-Cleaning
Media Label
K4218
Sewer Name
14 TRUNK "D"
City
LANCASTER
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 14
Page No.
21
Purpose
Routine Assessment
Project
WO_618867_TV14023_FEB2017
Material
NRCP
Shape
Circular
Height
10 in.
Width
10 in.
Upstream MH
14 0476
Downstream MH
14 0475
Dir. of Survey
Downstream
Length Surveyed
334.4 ft.
Total Length
334.4 ft.
Structural Index
3
Structural Quick
3L00
Structural Rating
198
O&M Index
2
O&M Quick
2L00
O&M Rating
132
Overall Index
3
Overall Quick
Overall Rating
330
Pipe schematic from manhole 14 0476 to 14 0475
MH: 14 0476MH: 14 0475downstream0 ft. MWM - Water Mark, 30 %of cross sectional area0 ft. AMH - Upstream Manhole, Survey Begins - 14 04760 ft. MWL - Water Level, 15 %of cross sectional area2 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start2 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start31.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"56 ft. TFA - Tap Factory Made Active, at 02 o'clock, -, within 8 inches of joint: NO, 6"80.2 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"108 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"133.1 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"157.2 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"181.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"209.8 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"233.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"258.4 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"282.4 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: NO, 6"311 ft. TFC - Tap Factory Made Capped, at 02 o'clock, -, within 8 inches of joint: NO, 6"334.4 ft. SAP - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Finish334.4 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish334.4 ft. AMH - Downstream Manhole, Survey Ends - 14 0475

Observation photos (2)

  • Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

    2 ft. - Surface Aggregate Projecting, from 08 to 04 o'clock, within 8 inches of joint: YES, Start

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Start

    2 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start

Observations (20)

DistanceCodeObservation
0MWM
181.3TFC
80.2TFC
2SAP
2DAGS
108TFC
311TFC
133.1TFC
334.4SAP
56TFA
209.8TFC
157.2TFC
334.4DAGS
233.7TFC
258.4TFC
334.4AMH14 0475
282.4TFC
0AMH14 0476
31.1TFC
0MWL

Properties (5)

additional_info
SC306720
custom_field_two
3
customer
LACSD
datetime
2017-01-23T04:09:57-08:00
sewer_category