Sanitation Districts of Los Angeles Countyt4 Spatial
Wastewater/Activity/PacpInspection/1.0Aug 2, 2016, 07:25 AM
  • 02 1478_02 1477 _20160802_013439.mp4

Date
08/02/2016
W/O
585991
Weather
Dry
Operator/Surveyor
J. HARTOOG
Sewer ID
Z00309
PipeID
P03922
Time
12:25 AM
Certificate
507-03-3386
System Owner
LACSD
Date Cleaned
Pre-Cleaning
Not Known
Media Label
K3670
Sewer Name
02 UNION PACIFIC TRUNK
City
COMMERCE, CA
Loc. details
Light Highway
Location Code
C
Use of Sewer
Sanitary Sewer
District
District 02
Page No.
16
Purpose
Routine Assessment
Project
WO_585991_TV02189_AUG2016
Material
Vitrified Clay Pipe
Shape
Circular
Height
15 in.
Width
15 in.
Upstream MH
02 1477
Downstream MH
02 1478
Dir. of Survey
Upstream
Length Surveyed
265 ft.
Total Length
265 ft.
Structural Index
2
Structural Quick
2100
Structural Rating
2
O&M Index
2
O&M Quick
2100
O&M Rating
2
Overall Index
2
Overall Quick
Overall Rating
4
Pipe schematic from manhole 02 1477 to 02 1478
MH: 02 1477MH: 02 1478upstream0 ft. AMH - Upstream Manhole, Survey Ends - 02 14780 ft. MGO - General Observation - CONNECTION AT THE MH 9 O'CLOCK ACTIVE0.3 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish4.6 ft. CL - Crack Longitudinal, at 01 o'clock, within 8 inches of joint: YES77.8 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"105 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"130.3 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"152.7 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"179.8 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"218.6 ft. TFC - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"257.8 ft. DAGS - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Start265 ft. AMH - Downstream Manhole, Survey Begins - 02 1477265 ft. MWL - Water Level, 5 %of cross sectional area265 ft. MWM - Water Mark, 10 %of cross sectional area

Observation photos (4)

  • Water Mark, 10 %of cross sectional area

    0 ft. - Water Mark, 10 %of cross sectional area

  • Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"

    46.4 ft. - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"

  • Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"

    112.3 ft. - Tap Factory Made Capped, at 10 o'clock, -, within 8 inches of joint: YES, 4"

  • Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock,  , within 8 inches of joint: YES, Finish

    264.7 ft. - Deposits Attached Grease, 5 %of cross sectional area, from 04 to 08 o'clock, , within 8 inches of joint: YES, Finish

Observations (14)

DistanceCodeObservation
187.2TFC
46.4TFC
265AMH02 1478
265MGOCONNECTION AT THE MH 9 O'CLOCK ACTIVE
264.7DAGS
0AMH02 1477
0MWL
112.3TFC
260.4CL
7.2DAGS
0MWM
85.2TFC
134.7TFC
160TFC

Properties (5)

additional_info
SC305550
custom_field_two
4
customer
LACSD
datetime
2016-08-02T00:25:00-07:00
sewer_category
Gravity